New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Selected PMP Project-Management-Professional Questions Answers

Page: 17 / 127
Total 1702 questions

Project Management Professional (2024 Version) Questions and Answers

Question 65

A project manager for a building construction project is planning to go on vacation

midway through the project execution phase. What should the project manager do first to

ensure the team is empowered and deadlines are met?

Options:

A.

Allow the team to make decisions to stay on schedule.

B.

Postpone the vacation to a different time.

C.

Ask the project sponsor to make any necessary decisions.

D.

Analyze the impacts and create a plan for team decision making

Question 66

A project manager is attending a progress meeting with a client The client requests a design change which might potentially add value to the project What action should the project manager take?

Options:

A.

Accommodate the change request to serve the client's needs

B.

Consult with team members and allow them to make a decision

C.

Convince the client not to make changes to the project

D.

Make transactional decisions focusing on the project goals

Question 67

During the third iteration of a project, the main sponsor retired from the company, and a new sponsor was appointed. The new sponsor is not familiar with the agile approach for project delivery, which leads them to request more control over the project team.

What should the project manager do?

Options:

A.

Schedule a meeting with the new sponsor in order to explain the agile approach and how teams are supposed to be self-organized.

B.

Schedule an emergency meeting with the project team so they fulfill every request that comes from the sponsor.

C.

Review the sponsor's request with the project team during the next daily review meeting in order to provide the requested control.

D.

Review the sponsor's request with the project team during the next iteration review meeting in order to obtain a team decision.

Question 68

A project manager has been assigned to take over an existing software project. The project manager inherited a lean team comprised of key stakeholders, subject matter experts

(SMEs), and senior developers. While reviewing the project status with the team, the project manager observes that the team seems to lack direction and enthusiasm.

What should the new project manager do?

Options:

A.

Ensure everyone performs their assigned tasks as planned.

B.

Organize frequent team building sessions and update the risk register.

C.

Meet with the project sponsor and propose a corrective action for the project.

D.

Encourage participation in decision making and empower the team.

Page: 17 / 127
Total 1702 questions