New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PMP Exam Questions Tutorials

Page: 38 / 127
Total 1702 questions

Project Management Professional (2024 Version) Questions and Answers

Question 149

A project sponsor commonly asks the project manager to skip project retrospectives due to time constraints However the project manager persists in running this critical ceremony by reducing the time for preparation and for discussion

What are two issues that these actions by the project manager could cause? (Choose two)

Options:

A.

A lot of discussions that yield no results or possibly too many results

B.

A lack of direction and motivation for the team in the workshop

C.

Lessons learned from other teams to not be considered

D.

Time management plan for the retrospective workshop to not be updated

E.

A focus on the negative and a disinterest in further improvements

Question 150

For the purposes of quality assurance a quality audit was conducted on the processes being used in the project execution plan. One of the nonconformance issues raised by the auditor was that attendance lists for the project risk review meetings were not available

Why is an attendance list important?

Options:

A.

It is standard practice on projects to conduct risk review meetings which should have records on meeting attendance

B.

The attendance list is evidence that risk review meetings were held with the appropriate project team members

C.

It is a record that shows the number of attendees in the meeting

D.

It is a document that is registered within the lessons learned register

Question 151

During the implementation stage of a project. a newly appointed team leader approaches the project manager to verify the team's tasks and schedule. The work did not go as planned due to the team leader's lack of management experience. This could cause delays for the project.

What should the project manager do?

Options:

A.

Ask the human resources director to appoint a senior team leader

B.

Inform the project sponsor about the possible delay

C.

Directly manage the project team to avoid project delays

D.

Provide mentoring to the newly appointed team leader

Question 152

The project manager is having difficulty obtaining approval of the project requirements because there is disagreement among the project stakeholders This issue is putting the project schedule at risk

What should the project manager do first to facilitate the approval of project requirements'?

Options:

A.

Review the project charter

B.

Perform a stakeholder analysis

C.

Identify the source of the disagreement

D.

Hold a team-building event

Page: 38 / 127
Total 1702 questions