A project sponsor commonly asks the project manager to skip project retrospectives due to time constraints However the project manager persists in running this critical ceremony by reducing the time for preparation and for discussion
What are two issues that these actions by the project manager could cause? (Choose two)
For the purposes of quality assurance a quality audit was conducted on the processes being used in the project execution plan. One of the nonconformance issues raised by the auditor was that attendance lists for the project risk review meetings were not available
Why is an attendance list important?
During the implementation stage of a project. a newly appointed team leader approaches the project manager to verify the team's tasks and schedule. The work did not go as planned due to the team leader's lack of management experience. This could cause delays for the project.
What should the project manager do?
The project manager is having difficulty obtaining approval of the project requirements because there is disagreement among the project stakeholders This issue is putting the project schedule at risk
What should the project manager do first to facilitate the approval of project requirements'?