Summer Certification Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PMP Leak Questions

Page: 4 / 14
Total 187 questions

Project Management Professional (PMP) July 2026 Update Questions and Answers

Question 13

A project team is working across different time zones and all team members are unable to attend the daily coordination meetings at the same time. The tasks are split

across teams working independently in different regions; however, there are task dependencies between the two teams.

What should the team lead do?

Options:

A.

Ensure all team members participate in the meetings regardless of time zone challenges.

B.

Ensure each team creates and accesses relevant project artifacts to manage dependent tasks.

C.

Check if additional meetings are required with a time suitable for both teams.

D.

Assign the dependent tasks to team members in the same time zone to avoid issues.

Question 14

During the first sprint review, the project sponsor requests an update to the product backlog. The team realizes that this may cause short-term resource constraints, but no additional budget is available.

What should the project team do?

Options:

A.

Set up another meeting to discuss details and include the technical team.

B.

Discuss the features added to the product backlog to confirm they are different.

C.

Schedule a meeting with the product owner and reprioritize the product backlog.

D.

Include this topic in the sprint retrospective and reevaluate the project resources.

Question 15

Agroup of specialists with years of experience is temporarily joining a project team. The project manager has been eager for their help in the production of a key

deliverable.

How should the project manager effectively lead these experienced team members?

Options:

A.

Provide constant supervision and monitor their progress on a daily basis.

B.

Provide reasonable flexibility and monitor their progress on a weekly basis.

C.

Ask the team members to provide training to the rest of the team and estimate the completion date.

D.

Ask the team members to provide an estimated completion date and review their work on that date.

Question 16

A project team is planning a university graduation ceremony. During a team meeting, a team member disagrees with the project manager on the prioritization of

project activities. The team member thinks that it would be more efficient to prioritize the sponsorship instead of preparing a budget since a budget template already

exists.

What should the project manager do?

Options:

A.

Meet with the individual and their manager to discuss activity concerns.

B.

Review the list of activities with stakeholders.

C.

Ask the team member to schedule a meeting with the sponsor.

D.

Consider the team member ' s opinion.

Page: 4 / 14
Total 187 questions