New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Free Access PMI PMP New Release

Page: 6 / 127
Total 1702 questions

Project Management Professional (2024 Version) Questions and Answers

Question 21

A project manager is leading a product development project that requires high involvement from several stakeholders. What should the project manager do to ensure this involvement?

Options:

A.

Evaluate the engagement needs of stakeholders.

B.

Distribute weekly status emails to stakeholders.

C.

Engage the sponsor on the behavior of stakeholders.

D.

Conduct weekly update meetings with stakeholders.

Question 22

According to the project contract the delivery date is approaching However one important material is still not on site The construction work will have to stop and wait for this special material, delaying the project.

What should the project manager do?

Options:

A.

Record it in the risk register

B.

Ask the client to help solve the problem

C.

Start procuring this material from another supplier.

D.

Engage the project team to look for alternatives to find a solution

Question 23

A large company has agreed on a business case for an environmental project. The

project will cause some major changes in their operations, such as reduction in paper use,

which will obviously affect all of the users.

What is the first thing the appointed project manager should do?

Options:

A.

Evaluate the impact to the users and create a plan to address it.

B.

Inform users about the new changes and ask for their collaboration.

C.

Ask all managers to collaborate implementing this change to users.

D.

Start implementing the change so that users will eventually get used to it.

Question 24

In an attempt to streamline project communications, a project manager established a shared portal for all stakeholders to get project information. The sponsor complained about this system and says that it is ineffective.

What should the project manager have done to prevent this situation from occurring?

Options:

A.

Analyzed the sponsor's communication requirements.

B.

Confirmed that the portal is providing adequate information.

C.

Verified that the project team is following the communications management plan.

D.

Ensured the sponsor had the necessary skills to use the portal.

Page: 6 / 127
Total 1702 questions