Big 11.11 Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Vce PMP Questions Latest

Page: 33 / 152
Total 2040 questions

Project Management Professional (2025 Version) Questions and Answers

Question 129

A business improvement opportunity to reduce energy usage has been identified.

The project manager has assembled a team that includes site engineers to deliver this project.

However, due to production imperatives, the site engineers may not be fully focused on the

project.

How should the project manager manage the team?

Options:

A.

Develop an approved responsibility assignment matrix (RAM) to confirm internal andexternal resource requirements.

B.

Commit each team member's time and deliverables and aim for overall projectcompletion.

C.

Continue the project implementation without the site engineers to ensure the scheduleis maintained.

D.

Contract external resources to fulfill the role of the site engineers who cannot support the project.

Question 130

A project manager is leading a project at a contracting company, and the project

team just completed an iteration. The product passed inspection, but an additional feature was added to the product. The customer notices the additional feature and thinks it will introduce new risks to the product.

What should the project manager do to avoid this situation in the future?

Options:

A.

Manage the scope baseline to influence the factors that drive change.

B.

Follow the proper change control process and evaluate the change for further impact.

C.

Work with the customer to ensure the feature adds value.

D.

Perform frequent reviews with the customer to ensure that the product is working asexpected.

Question 131

A project manager is appointed to manage an infrastructure project that spans

across several countries, including different time zones within a subregion. It is likely that most of the project team members will never meet, but they will have to collaborate to ensure deliverables are met.

What should the project manager do to ensure good collaboration between the remote project team members?

Options:

A.

Discuss the concerns with the project sponsor and modify the project charter to includemore budget for interactions.

B.

Plan a communication method and allow the project team members to virtually interact.

C.

Create a social media group platform for the team to create a supportive environment.

D.

Set the ground rules and identify a contingency plan in the risk register.

Question 132

During the planning for a long project, the project manager recognized that several

members of the team are new to their roles. How should the project manager incorporate this

into planning?

Options:

A.

Increase the overall project duration to account for the inexperienced team memberson the project.

B.

Ensure planning has accounted for replacing team members in new project roles whodo not deliver on project goals.

C.

Assess the training requirements and ensure time for professional developmenttraining by senior members.

D.

Revisit the project resource allocation to remove the inexperienced team membersassigned to the project.

Page: 33 / 152
Total 2040 questions