Spring Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PMI PMP Questions Answers

Page: 8 / 160
Total 2134 questions

Project Management Professional (PMBOK 7th Version) Questions and Answers

Question 29

A project manager is leading a project to modemize the information technology of a bank. The project manager needs to determine how the project stakeholders should communicate, and has discussed the various options with the project team.

What should the project manager do to communicate with the stakeholders?

Options:

A.

Provide updates to the project sponsor to review and distribute to each stakeholder.

B.

Use a single communication medium such as video teleconferencing to limit confusion.

C.

Use a variety of communication methods that respect cultural, practical, and personal preferences.

D.

Send frequent updates via email to each stakeholder because this is an information technology project.

Question 30

A project manager is assigned to a project that has a tight schedule. Due to recent market changes the marketing team has identified that a few features that were initially in the scope are no longer required

What should the project manager do?

Options:

A.

Advise the marketing team that at this stage of the project changes to the scope are no longer accepted

B.

Escalate the issue to the project management office (PMO) and make sure they understand the impact on the schedule due to the change

C.

Update the risk register with input from marketing and sales and highlight the benefits of the features m discussion

D.

Review the change request with the project stakeholders and evaluate the impact of the scope reduction

Question 31

A project team member is providing updates to assigned work and reports a task as complete, As the project progresses, it is observed that the task is not fully complete.

What should the project manager do moving forward?

Options:

A.

Provide clear expectations around task requirements.

B.

Review the task list with the team on a regular basis,

C.

Provide templates for the product owner to use in the future.

D.

Review the task with the sponsor to see if they are satisfied.

Question 32

A project manager is managing a project that is going to deliver a new risk platform. This platform will enable data-driven and new risk market models to ensure compliance with new regulations. The regulatory requirements for the models are released continuously and are not fully fixed yet. The project manager is reviewing the risk register and added a few new

Hems

Match the risks on the left lo the correct category on the right.

Options:

Page: 8 / 160
Total 2134 questions