Big Halloween Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Project-Management-Professional PMP Book

Page: 23 / 45
Total 594 questions

Project Management Professional (2025 Version) Questions and Answers

Question 89

A project is in the execution phase and there are disagreements between two key stakeholders about the project's scope. One stakeholder is adamant about expanding the scope and the other stakeholder is content with the current arrangement.

What should the project manager do?

Options:

A.

Escalate the stakeholder's conflict to senior management so they can resolve the issue.

B.

Schedule a one-on-one discussion with each stakeholder to understand their concerns.

C.

Schedule a meeting with both stakeholders to encourage dialogue and reach a decision.

D.

Suggest that the two stakeholders meet together to agree upon a project scope.

Question 90

In a project, one team member has been asking for directions and what actions to take on many tasks. As a result, the team member has performed slowly in project delivery.

What should the project manager do to help this team member?

Options:

A.

Assign another senior team member to coach the team member.

B.

Empower the team member to make decisions.

C.

Mentor the team member on a regular basis.

D.

Address the team member's performance accordingly.

Question 91

A human resource (HR) acquisition process for a large project has recently changed. One major process change includes the approval of the financial manager and the recruitment manager. This change to the process implies longer processing. The project urgently needs new resources.

What should the project manager do?

Options:

A.

Adapt the resource management plan and ask for financial approval before sending it to the customer.

B.

Assess the impact of the change and review the project management plan for next steps.

C.

Ask the financial manager to delay implementation due to potential project delays and penalties.

D.

Review the project schedule to determine which technique will reduce impact on project duration.

Question 92

A project manager is assigned to a long-term project. The project manager came across a government debate over a new law that may affect the project.

Which first two actions should the project manager perform? (Choose 2)

Options:

A.

Create a change request to discuss with the change control board (CCB).

B.

Perform a risk identification process with the project team.

C.

Ask the project sponsor for additional budget for contingency.

D.

Consult with the project stakeholders and evaluate the impact.

E.

Discuss the possible impacts with subject matter experts (SMEs).

Page: 23 / 45
Total 594 questions