Big Halloween Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Pass PMP Exam Guide

Page: 11 / 45
Total 594 questions

Project Management Professional (2025 Version) Questions and Answers

Question 41

A project manager was recently assigned to a banking IT project. The project team has been developing products using a predictive approach for more than 10 years, but management wants the team to change to an agile approach. The project manager met with the team to introduce the agile approach. Most of the team members complained about changing approaches because the performance of this team has always been above average among the IT teams in the bank.

Which two actions should the project manager take? (Choose two)

Options:

A.

Interview the most resistant team members to persuade them to try to accept an agile approach.

B.

Conduct training sessions with the team so that the team can understand what the agile approach and mindset are.

C.

Ask the team to identify the product backlog and create a kanban board for the team to manage and follow the approach.

D.

Meet with management to explain the team's resistance to the agile approach and request that they formally ask the team to implement agile.

E.

Brainstorm with the team to understand the specifics of the team's project and to identity possible alternative approaches for the team.

Question 42

A project manager notices that the project team is encountering product issues while coding client-specific developments. The project manager foresees delays to the project's timeline because of these product issues.

Which methods should the project manager use to communicate project delays and other difficult messages to stakeholders?

Options:

A.

Oral feedback, project meetings, and reporting

B.

Project meetings and reporting

C.

Project meetings and oral feedback

D.

Written feedback, project meetings, and reporting

Question 43

A drone manufacturing company is designing its first drone. The new project architect has called the project manager to review the project scope. The architect wants to reshuffle the scope and schedule to test the drone functionality first. The project team disagrees because the scope has already been approved and any change might affect the timelines set by the CEO.

What should the project manager recommend?

Options:

A.

Review the timelines with the architect and invite the CEO to the meeting to make sure all the stakeholders are involved.

B.

Reject the review as the completed project timeline is set by the company's CEO and has already been approved.

C.

Agree to review the architect's new proposal to assess the impact on the timelines set by the CEO.

D.

Register an issue in the log regarding the timeline delay to the CEO's approved plans before agreeing to change the project scope.

Question 44

A product owner is continuously adding requirements to a project that will significantly impact project delivery. How should the project manager address this?

Options:

A.

Reprioritize the work and add all new work to the product backlog.

B.

Check with the project team about their availability to continue project work.

C.

Consult with senior managers on how to address this to ensure the product owner's expectations are fully met.

D.

Ask the product owner to reprioritize and consider the project done when the highest priorities are delivered.

Page: 11 / 45
Total 594 questions