New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Project-Management-Professional PMP PMI Study Notes

Page: 30 / 127
Total 1702 questions

Project Management Professional (2024 Version) Questions and Answers

Question 117

A project manager is leading a project which shows a trend to exceed the cost baseline What should the project manager do first to manage the budget?

Options:

A.

Ask the project sponsor for assistance in getting the budget back on track

B.

Meet with the project team to analyze the actual cost to determine deviations

C.

Inform the stakeholders that the project will be finished over budget.

D.

Issue a change request including the analysis to increase the budget

Question 118

During the design phase, a project manager realizes that the project will benefit from using adaptive tools The effectiveness of this approach has been proven in past projects inside the organization

What should the project manager do first?

Options:

A.

Update project documents to include adaptive tools and artifacts and plan the first iterative session

B.

Contact the project sponsor and request new team members who are familiar with adaptive projects

C.

Confirm team capabilities before introducing adaptive tools and artifacts to the project

D.

Freeze the design stage and look for an external resource to run iterative design at extra cost

Question 119

The project manager started a new project and must ensure that the team members and stakeholders are adequately trained. After an interview with the team, the project manager discovers that all resources have experience in different agile methodologies

What should the project manager do?

Options:

A.

Make sure the project team is aware of all agile techniques

B.

Skip the training because the team already understands agile

C.

Ensure the team has a common understanding of agile

D.

Teach one agile methodology fully and completely

Question 120

The project sponsor of a major initiative is consistently changing the prioritization of modular work packages The team is used to three week sprints and is becoming increasingly frustrated with the daily changes in scope>

What should the project manager do?

Options:

A.

Move to a Kanban strategy so that work can be reallocated more easily

B.

Decrease the sprint cycle to the average repriontization request by calculating it in days

C.

Set up a meeting with the project team and ask for their opinion on what to do

D.

Set up a meeting with the sponsor to explain the importance of keeping a strict sprint cycle

Page: 30 / 127
Total 1702 questions