Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Project-Management-Professional PMP Updated Exam

Page: 14 / 45
Total 594 questions

Project Management Professional (2025 Version) Questions and Answers

Question 53

A project manager works for an organization that intends to begin using agile delivery, but there is a lack of support from some business units. The project manager needs to address the lack of trust in agile.

What should the project manager recommend?

Options:

A.

Implement and establish an agile framework for the project.

B.

Hire a team of contractors for agile project delivery.

C.

Define detailed work instructions for agile project delivery.

D.

Negotiate special arrangements for an agile pilot project.

Question 54

A project manager is acting as a servant leader and is struggling to make deadlines on a critical roadway construction project that is falling behind schedule due to a lowperforming team. In order to get the project back on track, what should the project manager do first?

Options:

A.

Empower the team members to conduct their job activities and hold each person accountable to improve the schedule.

B.

Notify the project sponsor that the team is underperforming and request additional resources to compress the schedule,

C.

Contact each team member to inform them that further schedule slips will not be tolerated by the project sponsor.

D.

Begin holding daily meetings to assign each team member discrete tasks with specific due dates.

Question 55

A project is nearing completion when a critical resource can no longer work on the project. A temporary replacement is brought in from an external company to take over the role; however, complaints are soon received from other team members about this person's unprofessional conduct and behavior.

What should the project manager do first?

Options:

A.

Discuss the team charter with the new team member to align them with the agreed-upon conduct within the team.

B.

Report the new team member to human resources (HR) for disciplinary actions.

C.

Hold one-on-one meetings with the new team member and the rest of the team members to align the team charter.

D.

Ask the contracting agency to replace the temporary team member.

Question 56

Due to contractual issues, a key team member cannot travel to the project location for a design review meeting.

What should the project manager do?

Options:

A.

Consider setting up a virtual meeting with the team for the design review.

B.

Ask the project sponsor if another team member can participate instead.

C.

Solve the contractual issues before continuing with the design review meeting.

D.

Inform the stakeholders and demand an immediate solution from the project sponsor.

Page: 14 / 45
Total 594 questions