Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PMI PMP Online Access

Page: 45 / 45
Total 594 questions

Project Management Professional (2025 Version) Questions and Answers

Question 177

A project manager is appointed to a project that has just been approved. The project manager has extensive experience in hybrid projects, and the project team has performed many projects within a predictive framework. However, the project sponsor believes that the project needs to be executed using agile approaches.

What should the project manager do to select the most effective project framework?

Options:

A.

Adopt an agile framework to agree with the project sponsor.

B.

Perform a market evaluation with key stakeholders and determine the best approach.

C.

Evaluate project characteristics with the project team and adopt the most suitable framework.

D.

Suggest using a hybrid approach to the sponsor for project execution.

Question 178

A project team wants to change a delivery approach for a project. Team members explain the need for a review of the information-sharing approach to ensure efficient information exchange during the project.

What should the project manager do?

Options:

A.

Ask the project sponsor to decide on the best communication strategy.

B.

Review the stakeholder engagement plan with the project team.

C.

Ask the project sponsor to approve funding for a collaboration tool.

D.

Review the communications management plan with the project team.

Page: 45 / 45
Total 594 questions