New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PMI PMP Online Access

Page: 45 / 127
Total 1702 questions

Project Management Professional (2024 Version) Questions and Answers

Question 177

A project manager primarily works on implementation projects Depending on the deliverable, the project manager is able to estimate the time line based on previous projects. The project manager now receives a project that is different from the previous implementation projects.

What should the project manager do next?

Options:

A.

Refer to the previous protect they worked on and base the estimate on that

B.

Use expert judgment to estimate the schedule and then adjust the schedule as the project progresses

C.

Ask the project management office (PMO) by when the project can be completed and use that date as the project time line

D.

Break down the project into smaller tasks and estimate the durations of the activities

Question 178

Ai the start of a project, the sponsor declares that demonstrating benefits from the product will be extremely important. The project sponsor calls a meeting with the project manager and the project leadership team to discuss the best approach because the project has a high degree of uncertainty and many changes are expected.

What should the project manager propose?

Options:

A.

Develop requirements and designs to support a faster product release.

B.

Emphasize the adoption of a predictive approach to minimize ambiguity.

C.

Recommend an agile approach so the project can be delivered iteratively.

D.

Outsource development of the product to a third party with more experience.

Question 179

On a recently completed prefect a project manager noticed that some of the subcontractors approached the client directly with questions. These subcontractors had a previous direct reporting relationship with the client. The project manager is now in the initial stage of a new project with the same subcontractors and client.

How should the project manager set up communications?

Options:

A.

Inform the client that all communications moving forward will go through the project manager

B.

Ensure that the communications management plan covers contractual obligations

C.

Consult the communications management plan from a recent project that has been closed

D.

Update the communications management plan to allow the subcontractors to communicate directly with the client

Question 180

A customer calls the project manager to express concern about a project team

member who has been making changes within the live environment without approval. The

team member mentioned that the customer called and asked them to make the changes.

What should the project manager do next?

Options:

A.

Reinforce the value of documenting and approving all change requests and ask the

customer to issue these through the agreed channels.

B.

Organize a meeting to mediate the relationship between the customer and the team

member to ensure no feelings are hurt.

C.

Ask the customer to email all requests directly to you and you will ensure they are

actioned by the correct team member.

D.

Explain to the customer that the team member was just trying to help and the changes

can be reverted if necessary.

Page: 45 / 127
Total 1702 questions