Big 11.11 Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Online PMP Questions Video

Page: 25 / 152
Total 2040 questions

Project Management Professional (2025 Version) Questions and Answers

Question 97

A project manager has noticed that a critical team member is consistently arguing

with a client. This has started to have a negative effect on the meetings.

How should the project manager address this?

Options:

A.

Explain the impact of the scenario to the project team member.

B.

Remove the project team member from all future meetings.

C.

Talk to the client privately to highlight the situation.

D.

Recommend a performance improvement plan to the project team member.

Question 98

After difficult negotiations, a customer committed to pay the cost for changes to the

project scope. The team seems unhappy as the project completion time will take longer than

previously scheduled.

How should the project manager support the outcome of the new agreement?

Options:

A.

Motivate the team and deploy the necessary resources.

B.

Find a way to maintain the project schedule.

C.

Impose authority on the project.

D.

Request additional resources from the sponsor and motivate the team.

Question 99

A company has transitioned and is now delivering projects using a hybrid approach instead of a predictive approach. The distributed project team's knowledge of agile is varied. The project manager feels the new methodology will impact the timely delivery of the project.

What should the project manager do?

Options:

A.

Ask to execute the project with a predictive approach since there is a budget and schedule risk

B.

agile tools and techniques used m the defined hybrid methodology for consistent application by all team members

C.

Use the predictive approach tor team members who are not knowledgeable m agile project delivery practices

D.

Use crashing to reduce the critical path to ensure enough buffer to include the impact of the agile methodology update

Question 100

A system migration project is in its closing stage. The project manager is being pressured to close the project The project manager communicated to all stakeholders; however, the last department to migrate indicated that they have not received the notification

What should the project manager do?

Options:

A.

Report the issue during the next status meeting at the end of the week

B.

Escalate the issue to the project sponsor and upper management

C.

Close out the project and tell the manager to open a service desk ticket

D.

Log the issue and assign it to the project team member(s).

Page: 25 / 152
Total 2040 questions