Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Download Latest PMP Questions

Page: 44 / 45
Total 594 questions

Project Management Professional (2025 Version) Questions and Answers

Question 173

During a meeting with the customer, it was observed that the features delivered during the last few iterations were not meeting the planned expectations.

What should the project manager do?

Options:

A.

Ensure a continuous feedback environment is leveraged to improve the quality and overall satisfaction.

B.

Review the requirements and instruct the team to develop the deliverables according to the documentation.

C.

Mentor the team members and ensure they perform peer reviews of their work before implementation.

D.

Utilize the retrospectives to identify issues in the development phase that may cause deliverables to not be accepted.

Question 174

A project manager is implementing a project similar to a previous one that required strict adherence to occupational health and safety (OHS). Both projects are for the same client whose business environment is highly regulated. However, this time the client does not appear to be concerned about OHS requirements.

What should the project manager do first?

Options:

A.

Relax the OHS requirements as the client is not concerned.

B.

Discuss the OHS requirements with the client.

C.

Apply the same OHS requirements as the previous project.

D.

Discuss the OHS requirements with the regulatory organization.

Question 175

A project manager is working in a constantly changing business environment. In order to address this situation, the project manager has decided to use a collaborative leadership style.

Which landscape describes the project environment?

Options:

A.

High accountability, little authority

B.

Available resources, bad roadmaps

C.

Good roadmaps, little accountability

D.

Enough authority, insufficient resources

Question 176

An agile team is funded for a fixed 6-month period. The sponsor's request will take at least 12 months to complete.

What should the project manager do?

Options:

A.

Inform the sponsor that the team is unable to complete the requests due to a lack of funding, and defer the project.

B.

Prioritize the scope items to determine the duration needed for a minimal viable product (MVP) and adjust the funding request.

C.

Have the team work on the list of requests from the sponsor without modification until the 6-month period ends.

D.

Request the team complete all scope items, with the assumption of securing additional funding within 6 months.

Page: 44 / 45
Total 594 questions