Project Management Professional (2024 Version) Questions and Answers

Question 77

A project manager is responsible for providing a budget estimate for a long-term project that will be executed over several years. Which essential task should the project manager implement at this phase?

Options:

A.

Include key risks in the cost baseline.

B.

Perform an analogous estimate.

C.

Perform a bottom-up estimate.

D.

Include projected inflation rates.

Question 78

A project manager is managing a megaproject. The project stakeholders are from different geographical areas and have diverse cultural and social backgrounds. The project manager wants to improve team productivity to realize more effective and efficient results.

Which action should the project manager take?

Options:

A.

Empower team members to participate in decision-making and take ownership of actions.

B.

Implement a flexible work schedule policy to eliminate the time zone problems among stakeholders.

C.

Encourage team members to network so that they know each other's cultural backgrounds.

D.

Provide a relaxed work schedule policy and encourage team members to work from home.

Question 79

During a project review meeting, the project sponsor is worried that the protect may not be delivering results as planned Based on that the project manager is evaluating the project status. What information should the project manager use as an indicator that the project is actually delivering value?

Options:

A.

Stakeholders are satisfied with the current status.

B.

The project is under budget and on schedule

C.

The project is aligned with the project charter

D.

The protect is aligned with the benefits management plan

Question 80

During the execution phase, the project manager discovered that the deliverables

are not meeting the quality specifications requested by the main stakeholder. This has

caused the schedule performance index (SPI) to deteriorate from 0.98 to 0.72 and the cost

performance index (CPI) from 1.5 to 1.1.

What action should the project manager take to mitigate the issue of the deliverables being

rejected during the next iteration?

Options:

A.

Submit a change request to prioritize resolutions for the quality issue to minimize the impact on the rest of the deliverables.

B.

Reinforce the definition of done (DoD) during sprint planning so that the team has a common understanding of expectations.

C.

Assure that the product backlog is properly prioritized to avoid dependencies that cause rejection.

D.

Create a dedicated sprint to complete all of the pending specifications from previous sprints.