New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Free PMP Questions Attempt

Page: 42 / 127
Total 1702 questions

Project Management Professional (2024 Version) Questions and Answers

Question 165

A junior staff member was recently assigned to the team. The new team member tells the project manager that they are confused because they are not familiar with what is expected of them on the project

What should the project manager do to assist the new team member?

Options:

A.

Advise the new team member to enroll in project management training.

B.

Instruct the new team member to review the responsible, accountable consult, and inform (RACI) matrix before asking for help

C.

Advise the new team member to review the project charter and stakeholder engagement plan.

D.

Review the resource management plan and provide mentoring to the new team member if necessary

Question 166

A project manager meets with external stakeholders to explain the objectives and outline expectations for a new project. A key stakeholder appears to support the project, with the condition that other unrelated projects will receive financial support Due to cultural sensitivities the project manager is reluctant to be direct with the key stakeholder on this matter The project cannot proceed without the support of this stakeholder.

What should the project manager do?

Options:

A.

Proceed with the project without allowing scope creep to occur

B.

Use the contingency funds to provide support for the requested projects

C.

Cancel the project since the stakeholder's request is out of scope

D.

Inform the sponsor and document the request in the stakeholder engagement plan

Question 167

A project manager is leading an in-house company project in its very early stages This current project is similar to another project that ended a year ago

What should the project manager do to analyze the involved stakeholders?

Options:

A.

Lower the priority of stakeholder engagement as the stakeholders already have knowledge of this kind of project

B.

Use lessons learned from the previous project as a guide for the current project's stakeholder register

C.

Refer to the stakeholder register from the previous project as it was similar to the current project

D.

Document in the risk register that the current project may have different

stakeholders than the previous project

Question 168

An agile project is running its fifth iteration out of eight After the last iteration planning the team was informed that there is a new competitor in the market and it is necessary to move faster to ensure market share is not missed What should the project manager do?

Options:

A.

Add the competitor's functionalities to the product backlog to improve the product

B.

Ask the sponsor to add more people to the team

C.

Help the team to find a new approach to launch the product as soon as possible

D.

Ask the team to increase the velocity to launch the product as soon as possible

Page: 42 / 127
Total 1702 questions