New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Pearson PMP New Attempt

Page: 49 / 127
Total 1702 questions

Project Management Professional (2024 Version) Questions and Answers

Question 193

A project, which has its execution phase planned m an iterative way has the following metrics for the first three iterations

One of the requirements for the project states that m order to get payment authorized fcx the project neither the SPI nor the CPl can be less than 0 95 What should the project manager do in iteration 4 to ensure the project is in compliance with the requirement?

Options:

A.

Schedule crashing

B.

Fast tracking

C.

Earned schedule

D.

Earned value

Question 194

A project manager is leading a progress review meeting when some stakeholders who are new to the project express concerns about not having access to previously shared deliverables. What should the project manager do?

Options:

A.

Document the new stakeholders' concerns in the meeting minutes.

B.

Schedule an ad hoc meeting with the new stakeholders to discuss concerns.

C.

Use social media environments to share the project information

D.

Use the project management information system (PMIS) to share information.

Question 195

A project manager has been working with the same group of stakeholders for 3 years using a predictive approach. The stakeholders have invested in many projects and are familiar with the approach Recently the organization has strongly encouraged all project managers to adopt an agile approach. This was announced 2 weeks before the project manager planned to kick off a large complex project with the same group of stakeholders.

What should the project manager do?

Options:

A.

Use the agile approach in the new project and schedule agile training for those stakeholders who are new to this approach

B.

Continue to use the predictive approach m the new project since it is the approach the stakeholders are familiar with using

C.

Share the pros and cons of adopting an agile approach for the new project only with the team and ask them to decide which approach to use

D.

Share and discuss the pros and cons of adopting agile with the stakeholders and choose the approach they prefer for the new project

Question 196

A project manager has experience working with a specific provider that has been

requested for an upcoming project. This provider often fails to meet deliverable dates; however, it is the only company with the specific experience required for the project.

What should the project manager do during the planning phase?

Options:

A.

A. Hire resources to obtain knowledge about the provider's specific capabilities.

B.

B. Add penalty clauses to the contract and update the risk register.

C.

C. Encourage the provider to work overtime with no additional costs to the project.

D.

D. Contract another provider with less experience and give them a chance to provide the deliverables.

Page: 49 / 127
Total 1702 questions