New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Project-Management-Professional PMP Passing Score

Page: 13 / 127
Total 1702 questions

Project Management Professional (2024 Version) Questions and Answers

Question 49

The portfolio management office wants to cut costs by suspending some ongoing

projects that do not directly support the organizational strategy. The project manager has invested too many resources into one of the projects to be suspended, but the portfolio

management office has not backed down on their plan.

What should the project manager do to continue the project?

Options:

A.

Meet with the project team and revise the project goals.

B.

Update the project charter to make it align with organizational strategy.

C.

Demonstrate the project alignment to the organizational strategy.

D.

Escalate the issue with the project sponsor to request support.

Question 50

For an ongoing project, match the key performance indicators (KPIs) on the left to the correct categories on the right.

Options:

Question 51

Due to a recent budget reduction, two team members were released from an agile

team. The customer is still expecting early results for the project.

Which two actions should the project manager take to align customer expectations? (Choose

two)

Options:

A.

Ask the agile team to review the updated sprint velocity with the customer.

B.

Ask the product owner to review the prioritized backlog with the customer.

C.

Ask the agile team to review and update the quality management plan with the

customer.

D.

Review the impediments log with the customer.

E.

Send a detailed project management plan to the customer.

Question 52

A project manager for an agile project wants to have a highly engaged team. How should the project manager achieve this objective?

Options:

A.

Be clear with directions and assignments so people stay focused and engaged with their work.

B.

Promote an environment where everybody knows what their contribution means to the project as a whole.

C.

Design a reward system to get people motivated by recognizing significant individual contributions from the last sprint

D.

Encourage continuous rotation of roles among team members to keep people motivated throughout project delivery.

Page: 13 / 127
Total 1702 questions