Big Halloween Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Helping Hand Questions for PMP

Page: 24 / 45
Total 594 questions

Project Management Professional (2025 Version) Questions and Answers

Question 93

A company is transitioning from using a predictive approach to using an agile framework on a project. The project sponsor is concerned about the level of uncertainty and how to determine the time and budget required to complete the scope.

What should the project manager do to address this situation?

Options:

A.

Communicate to the key stakeholders that the project baseline could not be estimated due to the new framework being used.

B.

Ask the project team to create a high-level budget baseline for the project and provide more detail only for the first project stages.

C.

Review organizational process assets (OPAs) for similar projects to determine the schedule, costs, and resources required to execute them.

D.

Refine the amount of work required for the project with the project team and perform a detailed project baseline accordingly.

Question 94

Following an investment decision-making meeting for a project, a change to the organizational structure takes place in a multinational company. Due to the organizational change, internal stakeholders are referring the project manager to various other personnel for approval of the project budget.

What should the project manager do to obtain approval of the project budget?

Options:

A.

Provide the decision executive with all of the project details and request budget approval from the appropriate person.

B.

Identify the right person with help from local management, present the project summary, and request budget approval.

C.

Approach each of the referred individuals separately and request approval of the project budget from the appropriate person.

D.

Obtain the latest organizational chart and send an email to the appropriate person requesting budget approval.

Question 95

A global and complex project is in the execution phase. Recently, there were executive board changes, and the executive sponsor is transitioning to a new role. The outgoing sponsor asked the project manager to speed up project completion of the current phase to ensure successful onboarding of the new sponsor.

What should the project manager do?

Options:

A.

Use the contingency budget to implement compression techniques to finish the current project phase early.

B.

Review the stakeholder engagement plan and determine the best course of action to take.

C.

Notify the outgoing sponsor that the project needs to be put on hold until the new sponsor is onboarded.

D.

Submit a change request to the change control board (CCB) to modify the end date of the current phase.

Question 96

A project manager is leading a diverse project team that includes new and experienced team members. A conflict has occurred between two team members. One team member prefers using digital tools for project communication. The other team member prefers in-person meetings and phone calls for communication.

What should the project manager do to manage this conflict?

Options:

A.

Arrange a team-building activity to foster understanding and open communication among the team members.

B.

Allow the team members to continue using their preferred communication tools and methods.

C.

Initiate a conversation with the team members individually to understand their situations regarding communication.

D.

Instruct the team members to adapt to the project's communication tools and methods.

Page: 24 / 45
Total 594 questions