Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Changed PMP Exam Questions

Page: 16 / 45
Total 594 questions

Project Management Professional (2025 Version) Questions and Answers

Question 61

A newly assigned team member immediately begins questioning operating procedures. This new team member wants the team to follow operating procedures that the team member had used previously. During assignments, the new team member begins using some of those processes and procedures and suggests these practices to other team members.

What action should the project manager take?

Options:

A.

Organize a training for the new team member on the processes the team is currently using.

B.

Speak with the new team member at the retrospective and discuss potential improvements.

C.

Formalize the new processes and implement the team member's proposed changes.

D.

Hold a team meeting on governance, operating policies, procedures, and practices.

Question 62

A project is near completion but it is behind schedule. The contingency budget has already being used, although the remaining budget should be

enough to complete the project. The only subject matter expert (SME) assigned to the project has been asked by their manager to solve a

problem in the operations department.

What should the project manager do?

Options:

A.

Escalate the situation to the project sponsor.

B.

Free the resource to handle the operations priority.

C.

Ask the manager to submit a change request.

D.

Design a negotiation strategy for this situation.

Question 63

A project steering committee meeting was arranged to approve a milestone of a project within two weeks. The project manager is informed that a new project executive will take over the project.

What should the project manager do first?

Options:

A.

Assess the risks with the team members.

B.

Submit a change request to the change control board (CCB).

C.

Evaluate the project impact and seek additional funding if necessary.

D.

Brief the new stakeholders on the current project status.

Question 64

A company is about to start a complex research project. Due to the level of uncertainty, the project manager recommends the use of a hybrid approach; however, the organization only has experience with predictive projects.

How can the project manager strategize the use of a hybrid approach to the organization?

Options:

A.

Present the benefits of a hybrid approach to key stakeholders to get their support.

B.

Create a project change request to execute the project using a hybrid approach.

C.

Send a letter to the project management office (PMO) requesting to use a hybrid approach.

D.

Submit a notification to the project team confirming they will be using a hybrid approach on the project.

Page: 16 / 45
Total 594 questions