New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Changed PMP Exam Questions

Page: 16 / 127
Total 1702 questions

Project Management Professional (2024 Version) Questions and Answers

Question 61

A company's leadership team has decided to invest in a new product using an agile approach The commercial and product teams have started the planning activity for this new venture Which three key factors does the project manager need in order to deliver this product? (Choose 3)

Options:

A.

High-level product backlog

B.

Key performance indicators (KPls)

C.

Product vision

D.

Schedule performance indexes (SPIs)

E.

Product roadmap

Question 62

A project manager is meeting with the project sponsor regarding a new project.

The project manager tells the sponsor that, as part of the communications management

plan, a weekly email will be sent with the status of the project, so the sponsor can be

informed of the progress. The sponsor indicates that the email is not necessary because

they will ask for a status update whenever it is needed.

What should the project manager do next?

Options:

A.

Advise the project sponsor to request a 15-minute meeting, whenever necessary, with prior notification.

B.

Agree to the project sponsor's request, but continue to copy them on the weekly email so they can be informed of progress in case it is needed.

C.

Tell the project sponsor that if they prefer to not receive the communication, there is no problem in removing them from the email distribution.

D.

Ask the project sponsor what sort of information is needed and agree on a frequency for the communication.

Question 63

In an agile project, the project manager notices that one team member rarely reports blockers during daily check-ins. Additionally, the team member is too shy to participate in team activities and prefers to provide status updates individually to the project manager.

How should the project manager rectify this situation?

Options:

A.

Review team culture and the personality traits of the individual to address status update gaps.

B.

Create a safe space for status updates and encourage the team to approach the project manager.

C.

Review the team status updates more thoroughly to address the gaps.

D.

Support team inclusion and change the format of status updates to email.

Question 64

A company Is helping their client launch an Innovative product. During the sprint review, the product owner identifies that the product does not include key features that were previously prioritized as part of the product backlog.

What should the project manager do next?

Options:

A.

Extend the sprint timeline so the learn can work on the missing feature.

B.

Inform the product owner that this issue needs to be escalated to the executive level.

C.

Collaborate with the product owner and the team to plan the following sprint

D.

Initiate the change request process to include these missing features.

Page: 16 / 127
Total 1702 questions