A newly assigned team member immediately begins questioning operating procedures. This new team member wants the team to follow operating procedures that the team member had used previously. During assignments, the new team member begins using some of those processes and procedures and suggests these practices to other team members.
What action should the project manager take?
A project is near completion but it is behind schedule. The contingency budget has already being used, although the remaining budget should be
enough to complete the project. The only subject matter expert (SME) assigned to the project has been asked by their manager to solve a
problem in the operations department.
What should the project manager do?
A project steering committee meeting was arranged to approve a milestone of a project within two weeks. The project manager is informed that a new project executive will take over the project.
What should the project manager do first?
A company is about to start a complex research project. Due to the level of uncertainty, the project manager recommends the use of a hybrid approach; however, the organization only has experience with predictive projects.
How can the project manager strategize the use of a hybrid approach to the organization?