Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PMP PMI Exam Lab Questions

Page: 27 / 45
Total 594 questions

Project Management Professional (2025 Version) Questions and Answers

Question 105

A project manager joins an existing project. One project stakeholder is unhappy with the frequency and types of project updates received and has made a request for more What should the project manager do next?

information to be shared.

Options:

A.

Inform the stakeholder to wait for the annual stakeholder review meeting

B.

Schedule a meeting with the stakeholder to better understand their request

C.

Update the project communications management plan immediately

D.

Consult the scope baseline document to track project updates

Question 106

A customer requests additional changes 1 day before the planned change date. How should the project manager respond to the change request?

Options:

A.

Reject the changes as the lead time is too short.

B.

Determine whether the project team is capable of making the changes.

C.

Review the additional changes and perform integrated change control.

D.

Check if the changes are covered in the statement of work (SOW).

Question 107

A scrum master is receiving conflicting status updates for the same task. How should an accurate status be obtained from the team?

Options:

A.

Encourage team members to work together.

B.

Establish a clear definition of done (DoD) for each task.

C.

Assign one person to be responsible for the task.

D.

Review the deliverable carefully and determine the right status.

Question 108

In a frequently changing project, the project manager discovers a customer requirement change during a daily meeting. What should the project manager do?

Options:

A.

Give the change to the scrum master to investigate how much additional effort the change will require.

B.

Tell the customer that the requirement change will be put into the next project phase if management approves.

C.

Validate the requirement change with the product owner and development team before redefining the scope.

D.

Escalate to management for approval since the change was not included in the original requirements.

Page: 27 / 45
Total 594 questions