New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

All PMP Test Inside PMI Questions

Page: 12 / 127
Total 1702 questions

Project Management Professional (2024 Version) Questions and Answers

Question 45

In the middle of an iteration a team member suggests a new method of doing things The method provides no value to the end customer, however it may help the team to work more efficiently The change may require several days of work to implement

How should the project manager respond to the suggestion?

Options:

A.

The change should be considered and immediately added to the product backlog.

B.

The change should be considered and presented to the project sponsor for approval

C.

The change should be considered because it will help the team work more efficiently

D.

The change should not be considered because it adds no value to the end customer

Question 46

A project manager is working on a large project with a very difficult client. During

the course of the project, the project manager realizes that if the project team had a little more time and funding to make some minor changes, the client could realize the benefits of 25% of the project outcomes early.

How should the project manager approach this?

Options:

A.

Concentrate on the current project milestones.

B.

Update the project management plan for this new work.

C.

Develop a business case and submit it to the client.

D.

Make all the changes and then show the client the results.

Question 47

The team architect resigned from the company. The new architect points out a

design flaw during a planning meeting that may potentially impact the final quality.

What should the project manager do first?

Options:

A.

Review the scope management plan.

B.

Update the design with changes.

C.

Request an architecture review.

D.

Update the quality management plan

Question 48

A project manager is managing multiple teams. One team member complains to the project manager about the favoritism shown by a team lead to another team member and cites multiple instances.

Risk Response Strategies Analyze if someone else could contribute Record the observations and move ahead Check for options to exclude the stakeholder

What should the project manager do to resolve the team member's concerns?

Options:

A.

Use the withdraw/avoid technique to allow the individuals to resolve the issue between themselves.

B.

Use a problem-solving approach and set up a discussion with the team lead and team member.

C.

Establish guidelines for team leads to ensure that all team members are appropriately treated.

D.

Provide direction to the team lead on how to resolve the issue with the team member directly.

Page: 12 / 127
Total 1702 questions