Summer Certification Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PMI PMP Based on Real Exam Environment

Page: 9 / 14
Total 187 questions

Project Management Professional (PMP) July 2026 Update Questions and Answers

Question 33

The client believes that a newly assigned team does not fit well and prefers the previous team, whom the client already knows. What should the project manager do?

Options:

A.

Share team contact information and previous project experience with the client.

B.

Introduce the new team to the client and invite the client to project demos.

C.

Ask management to honor the client ' s request by using the previous team.

D.

Explain to the client about team allocation processes that are based on project complexity.

Question 34

A project manager works for a communications company. The manager of the mobile equipment department is concerned about the current project ' s activities.

According to the current project management plan, the department will need to purchase special equipment, but the cost was not planned. The project sponsor insists

the project should move forward because customers will be impacted if the equipment is not available.

What should the project manager do?

Options:

A.

Escalate the conflict to the project sponsor.

B.

Use the contingency reserve to fund the equipment cost.

C.

Resolve the issue in favor of the department manager to continue the project.

D.

Estimate the cost of purchasing the equipment and submit a change request.

Question 35

A project manager is leading an important development project. A key deliverable has been completed but does not meet the quality standards defined in the quality management plan.

What should the project manager do?

Options:

A.

Return the deliverable and ensure that the reworked deliverable meets the quality standards.

B.

Approve the deliverable because it will not affect the project’s overall quality standard.

C.

Accept the deliverable and instruct the team to continue working without reporting the issue.

D.

Adjust the quality standards to align them with the deliverable’s current quality level.

Question 36

During the execution of a project, the product manager receives a new product feature request from the organization ' s highest revenue-generating client. The team

estimates the work will take three days.

What should the project manager do?

Options:

A.

Start a new sprint for the new feature immediately.

B.

Analyze whether the new feature can be incorporated into the next sprint.

C.

Fast-track the current sprint to include the new feature request.

D.

Create a new parallel sprint for the new feature.

Page: 9 / 14
Total 187 questions