Spring Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Project-Management-Professional PMP Syllabus Exam Questions Answers

Page: 39 / 160
Total 2134 questions

Project Management Professional (PMBOK 7th Version) Questions and Answers

Question 153

During project execution a project team member resigned and a new junior member joined the team To smooth the transition the project manager assigned a senior project team member to transfer knowledge and support the junior team member The project manager subsequently received feedback from the senior team member saying that the junior member submitted a poor-quality deliverable and should be removed from the team However the project manager checked that deliverable and found it met quality requirements

Which technique should the project manager use to resolve this issue?

Options:

A.

Smooth/accommodate

B.

Compromise/reconcile

C.

Force/direct

D.

Collaborate/problem solve

Question 154

A project team member has lost enthusiasm and is experiencing low morale for a

project they were once excited about. What should the project manager do?

Options:

A.

Escalate the issue to the team member's functional manager and request a responseas soon as possible.

B.

Meet with the team member to understand what the issues are and to provide support.

C.

Leverage other team members who are contributing and making the project a success.

D.

Have the team member transferred to another project and add other resources to theproject.

Question 155

A project manager is developing a project baseline schedule and has started to

assign team members to the project activities according to their function. What should the

project manager do in this phase?

Options:

A.

Develop project onboarding guidelines for the team members assigned to the project.

B.

Ensure that a kick-off meeting is planned and invite relevant stakeholders toparticipate.

C.

Ensure that lessons learned are considered as part of the project scheduledecomposition.

D.

Confirm that no conflicts exist in resource calendars with assigned activities on otherprojects.

Question 156

A project manager is leading a project in which key performance Indicators (KPls) are measured through earned value management (EVM). Match each measurement on the left with the correct category on the right.

Options:

Page: 39 / 160
Total 2134 questions