New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Complete PMP PMI Materials

Page: 41 / 127
Total 1702 questions

Project Management Professional (2024 Version) Questions and Answers

Question 161

The project team follows a hybrid framework for its delivery. During the execution of a project, the team learns of a new compliance requirement that has to be delivered before any other requirements

How should the project manager address this situation?

Options:

A.

Ask the team to include the compliance requirement in the current sprint and deliver it.

B.

Add the new compliance requirement to the backlog as the technical team does not have any capacity.

C.

Include the compliance lead in the stakeholders list and wait for the next status meeting

D.

Collaborate with the compliance team member to review and prioritize the requirement’s delivery

Question 162

A multinational company has a plan to expand their business into a new country where they currently have no presence A project manager is assigned to initiate this project

After reviewing the business case, what should be considered first when developing an appropriate implementation strategy?

Options:

A.

Acquire project resources from the new country to mitigate the risk of uncertainty

B.

Evaluate the environmental and regulatory factors and identify high-level risks and assumptions

C.

Identify and monitor the risks closely since the company does not have lessons learned for this country.

D.

Ensure that project sponsors are in agreement on the project deliverables and timeline during the project

Question 163

A project manager has been appointed to a multimillion-dollar project The project is considered to be high risk since no similar projects have been undertaken before and there is no historical data Some external stakeholders are reluctant to provide support

What approach should the project manager take?

Options:

A.

Examine the plans, processes, policies, and knowledge that are specific to the organization undertaking the project

B.

Establish dialogue with stakeholders on the project constraints, assumptions, and critical inputs

C.

Convince senior management to close the project since the project lacks sponsorship and is considered to be high risk.

D.

Host a project team meeting, then update the risk register and the project management plan

Question 164

A project manager is assigned to a project within a program. The high-level requirements of the project are known, but the priorities of some of the requirements are uncertain as they are interdependent on some other pipeline projects within the program.

How should the project manager prepare for the next steps of the project?

Options:

A.

Escalate to the management team to increase the timeline based on the complexity of the project

B.

Wait for the other project estimates before planning the schedule

C.

Prioritize and estimate the milestones for the high-level requirements based on historical data

D.

Ask the project management office (PMO) to estimate the tasks for all the projects and share the project management plan

Page: 41 / 127
Total 1702 questions