PMI PMI-ACP Actual Questions

Page: 27 / 36
Total 482 questions

PMI Agile Certified Practitioner (PMI-ACP) Questions and Answers

Question 105

An infrastructure team had to revamp so downstream channels could consume data from the data lake, thereby improving operational efficiency for the end customers. Which primary components should the product manager consider while plotting performance and dependencies on the product roadmap?

Options:

A.

Product vision, business objectives, themes, timeframes, and disclaimers

B.

Product improvements, resource management, risk management, and deadlines

C.

Product goals, strategic objectives, major features, and release plans

D.

Features, stages of development, technology and infrastructure, dependencies, and risks

Question 106

During a team meeting, conflicting opinions arise regarding the best approach to complete a project task. The project manager wants to ensure that the team can effectively handle these conflicts and come to a resolution that benefits the project.

What is an effective way to handle conflicting opinions in team meetings in an agile environment?

During a team meeting, conflicting opinions arise regarding the best approach to complete a project task. The project manager wants to ensure that the team can effectively handle these conflicts and come to a resolution that benefits the project.

What is an effective way to handle conflicting opinions in team meetings in an agile environment?

Options:

A.

End the discussion until there is consensus.

B.

Wait for the problem to resolve itself.

C.

Choose the option that is best for the team.

D.

Restate the positions to find what is in common.

Question 107

During a project's last iteration, an agile team struggled with a feature's delivery due to the lack of a required skill. The project has already incurred a five-day delay. A further delay of at least 10 days is anticipated.

What should the agile project leader have done to avoid this situation?

Options:

A.

Provided just-in-time training of the required skill to specific team members

B.

Lowered the feature's priority until a team member acquired the skill to build it

C.

Assigned the feature to another agile team that had members with the required skills

D.

Ensured that the team was comprised of cross-functional, generalized specialists

Question 108

An organization strives hard to accelerate value delivery by improving product design, development, and transition activities. What ways of working should the organization discontinue to become an effective player?

Options:

A.

Leverage continuous feedback from customers to seamlessly align delivery with requirements.

B.

Define software functionality by relying on the developers' experience designing similar system

C.

Engage end users in user acceptance testing to ensure the product meets their expectations.

D.

Educate end users and other stakeholders to understand desired outcomes through user stories.

Page: 27 / 36
Total 482 questions