Easter Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PMI-ACP Premium Exam Questions

Page: 33 / 36
Total 482 questions

PMI Agile Certified Practitioner (PMI-ACP) Questions and Answers

Question 129

A project's product owner asks the scrum master to facilitate the estimation activity. The scrum master then meets with the team and the product owner to clarify the user stories. Following the meeting, the team assembles and provides individual user-story estimates.

What technique did the team use?

Options:

A.

Lessons learned

B.

Wideband Delphi

C.

Formal point counting

D.

Planning poker

Question 130

A project team is working with an enterprise agile center of excellence (CoE) to transition to a Scaled Agile Framework (SAFe). Many of the team members are not familiar with the new methodology and are worried that it will lead to more work and scrutiny.

What should the agile team lead do to help ensure a smooth transition?

Options:

A.

Set up lunch-and-learn sessions with the team to provide overviews about the new way of working.

B.

Encourage knowledge sharing and transparency among the working team.

C.

Request the enterprise coach to help the team through the process

D.

Discuss with the team what will change and when and establish a process to address concerns.

Question 131

Following approval of a business case, a company will introduce a new mobile app for customers to place orders. Time to market is a key concern. The product has entered into the 3rd iteration, but the team is concerned because they feel the technical designs do not meet the agreed-on definition of done (DoD). An agile coach has been hired to help validate product delivery against business requirements.

What should the agile coach do?

Options:

A.

Incorporate quality assurance in the planning stage of product development.

B.

Schedule a dedicated meeting with the product owner to tackle this roadblock.

C.

Conduct a brainstorming exercise to get to the root of the issue and devise action plans.

D.

Conduct a retrospective meeting at the end of the current iteration to identity necessary improvements.

Question 132

During a retrospective, team members suggest process improvement ideas. The agile team lead knows that, while many of these ideas are different from standard practices, a few of them are good. What should the agile team lead do?

Options:

A.

Require the team to try only those ideas that will ensure success.

B.

Allow the team to try ideas, but remind them that results will be reviewed by high-ranking executives.

C.

Associate idea successes and failures with the team's incentive plan to ensure accountability.

D.

Encourage the team to try the ideas, even if failure may be the outcome.

Page: 33 / 36
Total 482 questions