PMI Agile Certified Practitioner (PMI-ACP) Questions and Answers

Question 69

An agile team consisting of eight members is in their 11th iteration of a project. In the last iteration, the team was not able to complete every scope item it had committed to before the demonstration.

Which approach should the agile lead take?

An agile team consisting of eight members is in their 11th iteration of a project. In the last iteration, the team was not able to complete every scope item it had committed to before the demonstration.

Which approach should the agile lead take?

Options:

A.

Coach the team to decompose the backlog activities to granular, simple tasks that are easier to estimate and complete.

B.

Evaluate the team's capacity and help them select user stories for the iteration based on 60% of their capacity utilization.

C.

Discuss options to add more people to the team so they can complete the tasks on time and within budget.

D.

Evaluate the team's capacity and help them select user stories for the iteration based on 80% of their capacity utilization.

Question 70

The agile team has failed to meet their iteration goal, and contention has developed between members. The agile leader would like to determine how to improve the team's productivity and morale.

How should the agile leader address this?

Options:

A.

Standup meeting

B.

Retrospective meeting

C.

Demo of the new features to energize the team

D.

Offsite meeting with stakeholders

Question 71

The product owner is working on an application that will be built in a data lake leveraging a data

integration and transformation software application. With a budget of US$17,000 remaining, how should the product owner allocate the money? (Refer to Exhibit A)

Options:

A.

Prioritize the features based on customer feedback and potential value.

B.

Focus on the reporting module since it has the highest estimated cost.

C.

Complete the data repository and reprioritize based on the remaininq budqet.

D.

Proceed with all of the planned features to ensure completeness.

Question 72

An agile team is working on a new product and is behind with their deliverables for the quarterly release. The team discovers new issues during each iteration. They start working on the critical issues and sometimes forget to update the backlog. This leads to confusion, delays, and occasional rework.

How should the agile practitioner improve the team’s productivity?

Options:

A.

Work with the team to ensure that both the product and iteration backlogs are up to date.

B.

Work with the team to ensure that the release backlog is in sync with the product backlog.

C.

Work with the team to ensure that the iteration and release backlogs are kept up to date.

D.

Work with the team to ensure that the product backlog is always kept up to date.