An agile practitioner is working on a project to migrate data from computer systems to another location. To accomplish this task, they need to run four activities sequentially that different teams are performing. The teams are migrating two systems per day, but the agile practitioner thinks that three systems should be done per day.
What can be done to improve process efficiency?
Midway through a project the product owner learns from the sponsor that a major component, which is already 20 percent complete, is unimportant to users. The component was part of the approved scope and a key selling point for the project
What should the product owner do next?
Toward the end of a project the product owner discovers that the project has a high probability of failure due to a critical feature not functioning as expected What should the product owner do?
During its first sprint, a new scrum team realizes that it has insufficient team members with test automation skills to effectively complete its stories. What should the team do?