Easter Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Ace Your PMI-200 PMI ACP Exam

Page: 6 / 36
Total 482 questions

PMI Agile Certified Practitioner (PMI-ACP) Questions and Answers

Question 21

The risk profile of a project has increased beyond the upper threshold of tolerance. The product owner and project leader meet to discuss an approach for dealing with this.

What should the team do next?

Options:

A.

Add risk mitigation tasks to the backlog, then prioritize in current and upcoming sprints

B.

Add risk mitigation time to each requirement

C.

Apply the 80/20 rule, reserving 20 percent of each sprint’s capacity for risk mitigation

D.

Hold all risks until they become issues, then add issue resolution tasks to the product backlog

Question 22

During an iteration, an agile team discovers infrastructure requirements that were not initially considered. What should the team do to effectively manage this?

Options:

A.

Rework the iteration scope to accommodate these requirements.

B.

Add these requirements into the product backlog for future consideration.

C.

Raise the discovery of these requirements as an issue, and escalate to management.

D.

Immediately start working on these requirements.

Question 23

A project team tasked with delivering a solution with extremely aggressive timelines is facing an issue with meeting their sprint velocity targets. To address this issue and bring the project back on track, what action should the team take?

Options:

A.

Perform value stream analysis to eliminate the processes with wastage.

B.

Reevaluate the minimum viable product (MVP) deliverables to remove high-risk stories and meet timelines.

C.

Adjust the story points included in each sprint to represent the actual velocity.

D.

Include high-risk stories in earlier sprints to deliver incremental velocity.

Question 24

A food company seeks additional business-to-business (B2B) revenues from some customers by

implementing purchase order (PO) functionality. To achieve this, the agile project team is exploring PO integration options (see item #3 in Exhibit A), as the product increment (PI) planning process is underway.

What should the project team do next?

Options:

A.

Use agile estimation techniques like planning poker or relative sizing for collaborative assessment.

B.

Break down the feature into smaller tasks or user stories for better assessment and incremental delivery.

C.

Analyze current system requirements and dependencies, including integration levels and regulatory compliance.

D.

Refer to past performance and historical data from similar projects to identity potential risks and challenges.

Page: 6 / 36
Total 482 questions