PMI ACP Changed PMI-200 Questions

Page: 25 / 36
Total 482 questions

PMI Agile Certified Practitioner (PMI-ACP) Questions and Answers

Question 97

During an iteration planning meeting, the team suggests changes to add product value that will require extra work and impact the schedule. What should the agile project leader do?

Options:

A.

Re-estimate the project.

B.

Finish the product as it was initially planned.

C.

Try to include as many changes as possible.

D.

Ask the product owner for approval to proceed.

Question 98

During a Kanban team's daily stand up, an agile coach observes that the team seems disinterested in the work status. While it appears that there are no issues with flow, there is a marked lack of attention to team effort. When the agile coach queries the team for reasons, members explain that work continues to be scheduled with no end in sight.

What should the agile coach do?

Options:

A.

Work with the team to determine points at which to celebrate its work.

B.

Provide the team with a break by scheduling a team event.

C.

Have the team increase work in progress (WIP) levels to more quickly complete the flow.

D.

Rejuvenate the team by temporarily reducing WIP levels.

Question 99

As user stories are developed, what should be done to record and update acceptance criteria?

Options:

A.

Add more user stories.

B.

Use sprint retrospectives.

C.

Update current user stories.

D.

Update new tasks in the project plan.

Question 100

An agile team is working on a new product. To ensure that all unknown issues are clarified before committing to the scope the team plans to work only on spike user stories for the next three sprints

What should the agile coach do in this situation?

Options:

A.

Ensure that the spikes identify the risks early in the project to increase the chances of success

B.

Ensure that the business sponsor accepts the proposal and agrees to fund the additional spike sprints.

C.

Recommend that, in the first sprint, user stories with higher priority be executed in addition to the spike

D.

Support the decision because release planning will be improved, and the product backlog can be better groomed after allspikes are executed

Page: 25 / 36
Total 482 questions