Free and Premium PRINCE2 Prince2-Foundation Dumps Questions Answers

PRINCE2 7 Foundation written Exam Questions and Answers

Question 1

Which is a purpose of the plans theme?

Options:

A.

To identify, assess and control any potential changes to the baseline

B.

To establish the project's structure of accountability

C.

To assess and control uncertainty

D.

To understand whether the targets are achievable

Buy Now
Question 2

Which is created during the Starting up a Project process?

Options:

A.

Project mandate

B.

Project management team role descriptions

C.

Communication Management Strategy

D.

Quality Register

Question 3

What problem may occur if projects are not aligned with corporate business strategy?

Options:

A.

The control of projects may be poor

B.

The outputs may be of poor quality

C.

The objectives of different projects may overlap

D.

The project management approaches used may differ

Question 4

Which is a purpose of the 'identify the risks' step within the recommended risk management procedure?

Options:

A.

To identify responses to risks documented in the business case

B.

To identify information about the project environment and objectives

C.

To identify the roles to be involved in risk management activities

D.

To identify uncertainties that may impact on the delivery of the project objectives

Question 5

Which are purposes of the quality theme?

1. To implement continuous improvement during the project

2. To establish how the project will ensure that products created will be acceptable to key stakeholders

3. To ensure that the project is desirable and achievable

4. To identify, assess and control uncertainty

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Question 6

Identify the missing words in the following sentence.

The 'managing a stage boundary' process should be executed [ ? ] a management stage.

Options:

A.

when a stage plan has been prepared for

B.

at the beginning of

C.

when all the delivery steps have been completed within

D.

at, or close to the end of,

Question 7

Which is a purpose of a lessons log?

Options:

A.

To record any lessons that are raised in checkpoint reports

B.

To document that corrective action is being taken

C.

To escalate lessons to the project board

D.

To raise improvements with project assurance

Question 8

Which role is responsible for ensuring the project is justified in terms of cost?

Options:

A.

Project manager

B.

Executive

C.

Senior user

D.

Senior supplier

Question 9

Identify the missing words in the following sentence.

When proposed changes [ ? ], the change authority must refer the decision back to the project board.

Options:

A.

are below the agreed change budget

B.

are objected to by team members

C.

are rejected by the change authority

D.

exceed the agreed change budget

Question 10

Which product describes the method the project will use to engage with corporate, programme management or the customer?

Options:

A.

Quality management approach

B.

Communication management approach

C.

Change control approach

D.

Benefits management approach

Question 11

Which is the first task of PRINCE2's recommended approach to 'defining and analyzing the products'?

Options:

A.

Creating a product flow diagram

B.

Writing the product description

C.

Writing a project product description

D.

Documenting the plan

Question 12

Which is a minimum requirement for applying the organization theme?

Options:

A.

Each member of the project management team must have a written role description

B.

The roles of the project management team must be combined, wherever possible

C.

The project manager must be appointed from the supplier organization

D.

The frequency of communication to the project's stakeholders must be documented

Question 13

Which theme provides all management levels within the project management team with mechanisms for monitoring and control?

Options:

A.

Progress

B.

Change

C.

Organization

D.

Quality

Question 14

Which is an objective of the 'directing a project' process?

Options:

A.

To review and approve a project mandate

B.

To ensure corporate or programme management has an interface to the project

C.

To define how risks, issues and changes will be managed

D.

To obtain approval for completed products

Question 15

To meet the minimum requirements for applying the progress theme, when must the business justification be reviewed?

Options:

A.

At the start of the project

B.

Throughout each stage

C.

When a change is raised

D.

In exception situations

Question 16

Which activity takes place within the Managing a Stage Boundary process?

Options:

A.

Produce Highlight Reports

B.

Take corrective action within the limits of a stage's tolerance

C.

Produce an Exception Plan

D.

Authorize a Stage Plan for the next stage

Question 17

Which level of management sets the project level tolerances?

Options:

A.

Project board

B.

Team manager

C.

Corporate, programme management or the customer

D.

Project manager

Question 18

Which process ensures that key roles and responsibilities are allocated before a decision is made to initiate a project?

Options:

A.

Managing Product Delivery

B.

Initiating a Project

C.

Managing a Stage Boundary

D.

Starting up a Project

Question 19

Which is an objective of the 'managing a product delivery' process?

Options:

A.

To ensure the business case is regularly reviewed

B.

To assess whether the stage products have been approved

C.

To deliver the planned specialist products within tolerance

D.

To request authorization to start the next stage

Question 20

Which should be provided by corporate or programme management before the Starting up a Project process commences?

Options:

A.

A Project Brief

B.

Sufficient information to identify the prospective Executive

C.

The Project Initiation Documentation

D.

Authority to initiate a project

Question 21

Identify the missing words in the following sentence.

The 'directing a project' process starts when [ ? ] and is triggered by the request to initiate a project.

Options:

A.

the 'starting up a project' process is completed

B.

the project mandate has been approved by the project board

C.

the project board has agreed the project strategies

D.

corporate, programme management or the customer have authorized a project

Question 22

What is a benefits management approach used to assess?

Options:

A.

How the project's products have performed when in operational use

B.

The effectiveness of the project strategies

C.

How the project has progressed against its plans

D.

The suitability of the project management team structure

Question 23

Which is a purpose of the Risk Register?

Options:

A.

Describe the risk management techniques and standards to be applied to the project

B.

Act as a central record of information relating to the identified risks for the project

C.

Act as a repository for informal issues

D.

List the responsibilities for achieving an effective risk management procedure

Question 24

Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project's threats and opportunities.

Options:

A.

change budget

B.

project budget

C.

project's cost tolerance

D.

project's risk tolerance

Question 25

What should be considered when defining the number of management stages in a project?

Options:

A.

When the team managers are available

B.

When key decisions need to be made

C.

When highlight reports will be submitted

D.

When project support will be available

Question 26

Which is a purpose of the change theme?

Options:

A.

To prevent change to baselined products

B.

To identify, assess and control any potential and approved changes to baselined products

C.

To establish mechanisms to monitor and compare actual achievements against those planned

D.

To assess and control uncertainty

Question 27

Which describes an off-specification?

Options:

A.

An interdependency between products that was previously unidentified

B.

The addition of an improvement to a product description

C.

A prototype demonstrating a possible design solution

D.

The production of more than the defined quantity of a specialist product

Question 28

If a project is part of a programme, which 'starting up a project' process activities are MOST likely to be reduced or eliminated?

Options:

A.

Appointing the project board and producing the project brief

B.

Planning the initiation stage and appointing the project manager

C.

Producing the additional role descriptions and validating the project product description

D.

Verifying the project approach and capturing previous lessons

Question 29

Which describes a characteristic of a project?

Options:

A.

It maintains business as usual profitability

B.

It provides a quality service to customers

C.

It involves a team with different skills

D.

It enables established and proven best practices

Question 30

According to PRINCE2, which characteristic is necessary for an effective project board?

Options:

A.

An ability to delegate

B.

An attention to detail

C.

A calm management style

D.

A 'problem-solving' approach

Question 31

Which is an objective of the Starting up a Project process?

Options:

A.

Identify who will be responsible for creating the Project Plan

B.

Agree how the project will be monitored and controlled after initiation

C.

Authorize the Project Manager to proceed with the initiation stage

D.

Agree how issues and changes will be identified, assessed and controlled

Question 32

According to the 'defined roles and responsibilities' principle, what must be represented in the project management team?

Options:

A.

Project board, project manager and project assurance roles

B.

Directing, managing and delivering levels

C.

Business, user and supplier interests

D.

Corporate, programme management or the customer parties

Question 33

Which is a purpose of the 'closing a project' process?

Options:

A.

To provide the project board with information to judge the success of a stage

B.

To confirm the project has nothing more to deliver

C.

To establish mechanisms to judge whether the project is still viable

D.

To establish mechanisms for forecasting project objectives

Question 34

Which is a factor when deciding the duration of a management stage?

Options:

A.

The work packages to be delivered

B.

The level of risk in the project

C.

The cost of the stage

D.

The number of products to be produced in the project

Question 35

What information should be recorded in the quality register?

Options:

A.

Planned activities to determine whether the products are fit for purpose

B.

Potential threats to the project's objectives and how they will be managed

C.

Lessons that the project will capture and use during the project

D.

Off-specifications that will occur during the project

Question 36

Which term is defined as the means by which an organization transitions from its current state to the target state?

Options:

A.

Change management

B.

change control

C.

Progress management

D.

Risk management

Question 37

Which is a purpose of the 'controlling a stage' process?

Options:

A.

To review the success of the project at the end of a management stage

B.

To agree work package acceptance and delivery requirements

C.

To produce regular highlight reports for the project board

D.

To re-plan the current stage and the project when requested

Question 38

According to the ‘exception management’ technique, when should the team manager raise an issue?

Options:

A.

When the team manager predicts that a product will cause a stage to exceed its time tolerance

B.

When the team manager identifies that a product is going to be delivered late

C.

when the team manager predicts that a product will cause a work package to exceed its time tolerance

D.

when the team manager identifies that the work package has already exceeded its time tolerance

Question 39

How does the ‘managing product delivery’ process ensure that the team manager’s perspective is provided in a work package?

Options:

A.

The work packages are defined by the team manager and supported by a team plan

B.

the work packages provided by the project manager are agreed by the team manager

C.

The team plans are checked by project assurance against the work packages

D.

The stage plan covering the work packages is created with input from the team manager

Question 40

Which is a benefit of applying the ‘tailor to suit the project’ principle?

Options:

A.

Project management becomes less bureaucratic

B.

The capability of leadership is strengthened

C.

The project environment complexity is reduced

D.

The number of outputs is reduced

Question 41

Which is 3 purpose of the ‘plans! practice?

Options:

A.

To enable an event that requires project management consideration to be controlled

B.

To provide the standards against which the project products can be quality controlled

C.

To provide the basis of control against which a project's progress can be monitored

D.

To enable control of opportunities and threats, that could Impact on delivery of the business objectives

Question 42

Identify the missing words in the following sentence.

The 'starting up a project" process is triggered when a [ ? J is available.

Options:

A.

project business case

B.

project mandate

C.

stage plan

D.

work package

Question 43

When tailoring PRINCE2 to suit the project, [?] may be changed to suit other standards or policies.

Options:

A.

Defined acceptance criteria

B.

the PRINCE2 principles

C.

the terminology used

D.

the number of themes applied

Question 44

Which action should the project manager take during the 'assessing issues' step?

Options:

A.

Create an exception plan tor project board approval

B.

Gain project board feedback on the Issue priority

C.

Consider the impact of alternative options for resolution

D.

Determine the initial priority of the issue that has been raised

Question 45

Identify the missing words in the following sentence.

Project assurance personnel [ ? ] the project manager.

Options:

A.

are able to overturn the decisions of

B.

must be accountable to

C.

should support

D.

report to the project board and

Question 46

Which is a benefit of using PRINCE2?

Options:

A.

It promotes consistency of project work and the ability to reuse project assets.

B.

It includes techniques for critical path analysis and earned value analysis

C.

It enables a project manager to be accountable for the success of a project

D.

It prevents any changes once the scope of a project has been agreed

Question 47

Which action should the project manager take to ensure effective progress management when a team manager is inexperienced?

Options:

A.

Increase the frequency of checkpoint reports

B.

Allow the team manager more flexibility to exceed cost tolerance

C.

Increase the frequency of event-driven controls

D.

Increase the frequency of escalations by the team manager

Question 48

How does applying the ‘focus on products’ principle help to ensure that stakeholder expectations are met?

Options:

A.

By providing a common understanding of the products required

B.

By providing the tolerances for the project manager’s objectives

C.

By providing roles descriptions for the project management team

D.

By providing the justification for the project

Question 49

Identify the missing word in the following sentence.

[ ? ] is the measurable decline resulting from a negative outcome.

Options:

A.

An exception

B.

A dis-benefit

C.

An off-specification

D.

A risk

Question 50

What should be recorded in a quality register?

1. Activities to ensure the products are fit for purpose

2. Identified threats and opportunities

3. Problems and concerns to be managed informally

4. Roles responsible for reviewing the project's products

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Question 51

What is an advantage of dividing the project into stages?

Options:

A.

Detailed plans can be prepared closer to the time events will take place

B.

the project board can delegate management of the project to team managers

C.

The project can be authorized by the project manager on a stage by stage basis

D.

The project brief can be updated towards the end of each stage

Question 52

The project board Wants to consider whether td continue to operate in the same way, of Whether to change operations by means. of a project.

In which step of ‘business case management technique should this be considered?

Options:

A.

Develop

B.

Check

C.

Maintain

D.

Confirm

Question 53

What is the result of the change derived from using the project’s product?

Options:

A.

Benefit

B.

Dis-benefit

C.

Outcome

D.

Output

Question 54

Which report must be used to inform the project board of a predicted deviation from agreed stage limits?

Options:

A.

End stage report

B.

Checkpoint report

C.

Highlight report

D.

Exception report

Question 55

In which process is the work to be done assigned to a team manager?

Options:

A.

Directing a project

B.

Managing a stage boundary

C.

Controlling a stage

D.

Managing product delivery

Question 56

What is an advantage of applying the 'learn from experience' principle?

Options:

A.

It allows the project board to delegate cost tolerances to the project manager

B.

It allows the project team to fully understand their roles and responsibilities

C.

It allows the project manager to delegate time tolerances to the team managers

D.

It allows the project team to identify improvements to be made during the project

Question 57

Which is a minimum requirement for applying the organization theme?

Options:

A.

The project's approach to engaging with its stakeholders must be defined

B.

Roles must be combined to reduce the number of individuals needed on the project

C.

During a procurement the senior supplier must be appointed from the customer organization

D.

The project team must change at each end stage of the project life cycle

Question 58

According to the 'continued business justification' principle, when is a justifiable reason for a project FIRST needed?

Options:

A.

After the executive has been appointed

B.

When authorized by the corporate, programme management or the customer

C.

Before work to start the project commences

D.

When an organization produces its business plans

Question 59

Which statement describes the context of the 'initiating a project" process?

Options:

A.

The project is viewed from the perspective of the project board in this process

B.

This process should result in key stakeholders being committed to the project

C.

This process is triggered by the assembly of the project brief

D.

The 'controlling a stage' process will start immediately after this process

Question 60

Which is an objective of the 'directing a project' process?

Options:

A.

To create the plan to deliver the project product

B.

To select and appoint the project manager

C.

To design the project management team roles

D.

To give authority to deliver the project product

Question 61

What does the communication management approach define?

1. How versions of products will be described on information sent to interested parties

2. How information should be sent to interested parties

3. How often information should be sent to interested parties

4. How the PRINCE2 roles will be combined during the project

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Question 62

How does the ‘managing product delivery’ process achieve its purpose?

Options:

A.

By agreeing requirements for how project work should be undertaken

B.

By producing highlight reports to enable the project board to oversee the work

C.

By requiring the project manager to produce and monitor team plans

D.

By escalating issues and risks that cannot be resolved within stage tolerance

Question 63

What 15the purpose of the ‘progress! practice?

Options:

A.

To review whether the use of the products is likely to lead to the expected benefits

B.

To define the roles and responsibilities for monitoring progress

C.

To measure actual achievements against the planned time and cost targets for the project

D.

To control events that could have a positive or negative effect on project objectives

Question 64

What must be produced to meet the minimum requirements when applying the change theme?

Options:

A.

A change budget for the analysis of change

B.

Records of the decisions made on all issues

C.

Documents recording the version of each product

D.

Status reports on all products being produced

Question 65

Based on a review of lessons reports from previous projects, some proposals have been made on how to apply PRINCE to a project:

Which role should be accountable for approving these proposals?

Options:

A.

Project board

B.

Project manager

C.

Project assurance

D.

Business layer

Question 66

Which is an objective of the 'controlling a stage' process?

Options:

A.

To review the business justification for the project

B.

To replan the current stage when directed

C.

To develop products to defined quality criteria

D.

To produce a learn plan for the work package

Question 67

How should the "managing a stage boundary' process be used towards the end of a project's final delivery stage?

Options:

A.

To plan the activities of the closing a project' process

B.

To implement any exception plan requests from the project board

C.

To create a benefits management approach for corporate, programme management or the customer

D.

To review an issue received from a team manager

Question 68

What is the change authority role permitted to authorize?

Options:

A.

Risks to the project

B.

Adjustments to the limits on the change budget

C.

Changes to stage tolerance

D.

Changes to the project that do not exceed a defined budget

Question 69

According to the ‘defined roles and responsibilities’ principle, how many categories of stakeholder interest need to be represented in the project management team?

Options:

A.

One

B.

Two

C.

Three

D.

Six

Question 70

Which principle helps to ensure that all changes to the outputs are agreed?

Options:

A.

Defined roles and responsibilities

B.

Focus on products

C.

Learn from experience

D.

Manage by exception

Question 71

According to the 'manage by exception’ principle, which statement about tolerances is CORRECT?

Options:

A.

Whenever authority is delegated to the project manager, the project board should set tolerances for the stage

B.

Whenever there is a forecast to exceed a tolerance, it should be escalated to the project board

C.

Whenever there is a forecast to exceed a tolerance, it should be resolved at the next monthly project board meeting

D.

Whenever authority is delegated to the team manager, the focus should be on delivering within time and cost tolerances

Question 72

Which action should the project manager take when reviewing progress to assess the 'health' of a stage?

Options:

A.

Capture lessons that may assist in the monitoring and control of this project

B.

Review the quality of the relationships in the organizational

C.

Increase the frequency of event-driven controls to monitor stage progress

D.

Identify whether issues are resolved in a timely manner or left unmanaged

Question 73

Which term is defined as the means by which an organization transitions to a desired future state?

Options:

A.

Change management

B.

Risk management

C.

Issue management

D.

Communication management

Question 74

According to the ‘manage by exception’ principle, which aspect of performance sets limits against the cost of aggregated threats?

Options:

A.

Risk

B.

Scope

C.

Quality

D.

Cost

Question 75

The project manager heeds to prioritize several criteria that the project product must meet in order to be acceptable in which step of the ‘quality management technique should this occur?

Options:

A.

Gathering user inputs

B.

Accepting products

C.

Describing the quality management approach

D.

controlling quality

Question 76

The project manager needs to plan the reviews to confirm whether the expected measurable improvements have been achieved.

Which management product should the project manager produce?

Options:

A.

Benefits management approach

B.

Business case

C.

Quality management approach

D.

End project report

Question 77

Which term is defined as being achieved as a result of the activities undertaken to facilitate the change?

Options:

A.

Outcome

B.

Benefit

C.

output

D.

Request for change

Question 78

How do issue management and change control relate to each other?

Options:

A.

Change control and Issue management are separate processes

B.

Issue management is part of change control

C.

change control is part of issue management

D.

issue management and change control are identical

Question 79

Which is a feature of an effective project team?

Options:

A.

It should rely on the team sitting together in order to easily build effective working relationships

B.

It should consist of people with a wide range of skills, abilities and viewpoints

C.

It should plan and control effective communications with the project's stakeholders

D.

It should consist of full-time team members who can focus attention on the project's needs

Question 80

Identify the missing word in the following sentence:

[ ?] is a prediction made by studying historical data and past patterns.

Options:

A.

A forecast

B.

A project baseline

C.

An exception

D.

A highlight report

Question 81

Which is a feature of PRINCE2?

Options:

A.

It is naturally right=sized to the scale of every project

B.

It promotes improving processes for every project

C.

It replaces the need to apply specialist Industry-specific lifecycles

D.

It focuses on completing the project on time as its main objective

Question 82

What does qualitative analysis of a risk assess, as a minimum?

Options:

A.

How soon each risk might occur

B.

The fallback plan for each risk

C.

The likelihood and the effect of each risk on objectives

D.

The speed with which the effect of each risk will be felt

Question 83

What is a temporary organization that is treated for the purpose of delivering Business Products according an-agrees business casa?

Options:

A.

A project

B.

A baselined product

C.

The project scope

D.

The business

Question 84

The team manager has organized a workshop with project stakeholders to define the detailed requirements for a number of outputs.

Which principle is being applied by the team manager as part of the 'people’ element when holding this workshop?

Options:

A.

Focus on products

B.

Tailor to suit the project

C.

Define roles, responsibilities and relationships

D.

Ensure continued business justification

Question 85

in the ‘starting up a project’ process, what is the PRINCE? name for a ‘request for proposal’ received by an external supplier?

Options:

A.

Project mandate

B.

Project brief

C.

Work package

D.

Project approach

Question 86

Which TWO are objectives of the ‘starting up a project’ process?

1. To create a common view of How the required quality will be achieved

2.To give authority to initiate the project

3. To appoint the resources needed to do the work to initiate the project

4. To ensure that projects are initiated based or agreed acceptance criteria for the project product.

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Question 87

Which process should be Used to confirm that the project continues to deliver against the strategic objectives?

Options:

A.

Managing a stage boundary

B.

Managing product delivery

C.

Initiating a project

D.

Closing a project

Question 88

When should the project baseline be updated in order ta meet the purpose of the 'issues' practice?

Options:

A.

When a request for change is recorded on the issue register

B.

When a business opportunity has been recognized

C.

When the project manager receives a request for change

D.

When a change has been approved by the change authority

Question 89

Which process defines the work to deliver the major products ensuring that an organization uses its resources effectively?

Options:

A.

Initiating a project

B.

Starting up a project

C.

Controlling a stage

D.

Managing product delivery

Question 90

Which control is time-driven?

Options:

A.

The creation of a highlight report

B.

The completion of the PID

C.

The creation of an exception report

D.

The end of the financial year

Question 91

What is the BEST reason to perform the risk practice?

Options:

A.

To ensure risks are assigned to people who will own and action them satisfactorily

B.

To establish a supportive risk culture to enable decision-making

C.

To ensure stop-go decisions at stage boundaries are risk-informed

D.

To identiDfy and manage risks to project objectives

Question 92

Which statement describes a purpose of the 'starting up a project’ process?

Options:

A.

To appoint people ta the major rales in the project management team

B.

Ta agree how a team manager will report progress

C.

To provide Information so that the business can understand the cost of delivering the project

D.

To provide management control Listen the project manager and the team managers

Question 93

The project manager needs to record the impact assessment for a specific business opportunity.

In which management product should the project manager record this?

Options:

A.

Issue report

B.

Issue register

C.

Risk register

D.

Quality register

Question 94

When does the ‘directing a project’ process start?

Options:

A.

When the project manager submits the project brief for approval

B.

When the request to authorize a project is received

C.

After the project has been authorized by the business layer

D.

After the project mandate has been received

Question 95

How should effective issue management be applied When changing management products?

Options:

A.

By changing the issue management approach at the end of each stage to reflect lessons

B.

By creating new versions of a management product when a change is approved

C.

By Implementing a change budget to fund changes to the project product

D.

By recording the required change to a management product as an off-specification

Question 96

The project manager needs to record what will make file Users satisfied with the final product

Where should the project manager record this?

Options:

A.

Quality register

B.

Project plan

C.

Project product description

D.

Quality management approach

Question 97

Which management product Soul guide the Project management team on how to manage multiple aspects of the project?

Options:

A.

Project initiation documentation

B.

Project plan

C.

Business case

D.

Exception plan

Question 98

The senior user needs to ensure that the outputs will be used effectively to achieve the autcomes and realize the benefits.

Which element of effective business case management is the senior user applying?

Options:

A.

Aligning products to business objectives and tolerances

B.

The business case lifecycle

C.

Establishing business justification

D.

Planning benefit reviews during the project

Question 99

The project manager needs to know whether the response to a threat to the project has been actioned.

Which should the project manager review?

Options:

A.

Risk register

B.

Product register

C.

Risk management approach

D.

Checkpoint report

Question 100

Which TWO are objectives of the closing a project: process?

1. To ensure the benefit reviews enable the project benefits to the confirmed

2. To update the business case so that the project hoard can decide whether to continue with the project

3. To ensure that the project team deliver the products to quality expectations

4. To hand over any open threats to operations

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Question 101

Which TWO are objectives of the ‘starting up a project’ process?

1. To provide an interface between the corporate layer and the project

2. To provide the required authority to initiate the project

3. To plan the work required for project initiation

4. To provide business justification for initiating the project

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Question 102

What is being addressed when the project manager plans to keep the CO2 emissions of the project aligned with the business strategy?

Options:

A.

Benefits sustainability

B.

Product sustainability

C.

Delivery sustainability

D.

Quality sustainability

Question 103

The project manager is acting as the team manager and needs to control the work of a team member who reports to them.

Which management product should the project manager use to control this work?

Options:

A.

A work package description

B.

The project management team structure

C.

A stage plan

D.

A work breakdown structure

Question 104

Which is a definition of management?

Options:

A.

Directing the execution of project tasks as agreed for the project

B.

Away of working that characterises a group of people

C.

Being accountable to the business for the success of the project

D.

The party responsible for commissioning the project

Question 105

Which is a description of a purpose of the 'managing product delivery’ process?

Options:

A.

To agree requirements for the delivery of specific products between the project manager and the team manager

B.

To report progress towards the delivery of a stage’s products to the project board

C.

To recognize that the project has no further contribution make towards achieving project objectives

D.

To plan how the project will approach the work to deliver the project products

Question 106

Which is NOT considered when defining risk tolerance?

Options:

A.

A Project Board's attitude towards risk taking

B.

The allocated risk budget

C.

An organization's risk appetite

D.

The amount of risk a Project Board considers acceptable

Question 107

When should the Project Board refer to corporate or programme management for a decision?

Options:

A.

The stage requires resources

B.

It is forecast that project level tolerance will be exceeded

C.

The Senior Supplier or Senior User needs to be changed

D.

Any request for change needs to be approved

Question 108

Which is a typical core activity within configuration management?

Options:

A.

Quality assurance

B.

Risk management

C.

Verification and audit

D.

Progress reporting

Question 109

Why is the Initiating a Project process used?

Options:

A.

To decide which project approach is suitable for the project

B.

To fully understand how the project objectives will be achieved before committing significant resources

C.

To produce the required Work Packages

D.

To enable corporate or programme management to give authorization to deliver a project

Question 110

Identify the missing word in the following sentence. The guiding obligations and good practices which determine whether the project is genuinely being managed using PRINCE2 form the [ ? ] of the method.

Options:

A.

Principles

B.

Themes

C.

Processes

D.

Techniques

Question 111

Which statement about the Directing a Project process is true?

Options:

A.

Provides a mechanism for the Project Board to assure that there is continued business justification

B.

Covers the day-to-day activities of the Project Manager

C.

Ensures there are regular progress meetings

D.

Begins on completion of the Initiating a Project process

Question 112

Why is it crucial that the Project Product Description clearly defines acceptance methods?

Options:

A.

Enables Project Assurance to authorize quality activities

B.

Defines how all project products will be reviewed and approved

C.

Defines how it will be proven that the completed project product meets the customer's expectations

D.

Provides confirmation that all project products have met their quality criteria

Question 113

Which statement about the quality review technique is FALSE?

Options:

A.

It enables a check to be made on a product's fitness for purpose

B.

It defines the quality responsibilities of the project team

C.

It supports the management of future changes by providing a baseline for a product

D.

It is used to gain wider acceptance of a product by involving key interested parties

Question 114

Which risk response type is appropriate to respond to an opportunity?

Options:

A.

Accept

B.

Fallback

C.

Exploit

D.

Transfer

Question 115

If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?

Options:

A.

Checkpoint Report

B.

Highlight Report

C.

Issue Report

D.

Product Status Account

Question 116

Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?

Options:

A.

Corporate group

B.

Project Board

C.

Project Assurance

D.

Executive

Question 117

Which process is triggered towards the end of the final stage when all the assigned work has been completed?

Options:

A.

Managing a Stage Boundary

B.

Managing Product Delivery

C.

Closing a Project

D.

Controlling a Stage

Question 118

Who should act as the communication channel between a project and corporate or programme management?

Options:

A.

Project Board

B.

Project Assurance

C.

Project Manager

D.

Project Support

Question 119

Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?

Options:

A.

Project Brief

B.

Project Initiation Documentation

C.

Project mandate

D.

Benefits Review Plan

Question 120

Which is NOT a purpose of a Benefits Review Plan?

Options:

A.

Define the period over which the cost-benefit analysis will be based

B.

Describe how to measure the performance of the project's products in operational use

C.

Define the scope, timing and ownership of the benefit reviews required

D.

Describe how to measure and confirm any benefits that are to be realised after the project is closed

Question 121

What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?

Options:

A.

Configuration Item Record

B.

Quality Register

C.

Highlight Report

D.

Checkpoint Report

Question 122

Which should be funded by a change budget?

Options:

A.

Increase in agreed scope

B.

Initiation stage

C.

Change Authority

D.

Handover activities

Question 123

What needs to be in place to ensure effective issue and change control?

Options:

A.

Configuration management system

B.

Manage by exception

C.

Quality planning

D.

Information needs for stakeholders

Question 124

What product defines the reporting requirements between the Project Manager and Team Manager?

Options:

A.

Project Brief

B.

Product Description

C.

Team Plan

D.

Work Package

Question 125

Which is an objective of the Closing a Project process?

Options:

A.

Prepare the plan for the next stage

B.

Assess any benefits that have already been realized

C.

Produce a Benefits Review Plan to identify what benefits are expected

D.

Check that all benefits are realized before closing a project

Question 126

Which is an objective of the Managing Product Delivery process?

Options:

A.

Sign-off completed Work Packages

B.

Ensure the Business Case is kept under review

C.

Report progress to the Project Board

D.

Ensure that work on products is authorized and agreed with the team

Question 127

What theme provides all management levels within the project management team with mechanisms for monitoring and control?

Options:

A.

Progress

B.

Change

C.

Organization

D.

Quality

Question 128

Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.

Options:

A.

project cost tolerance

B.

stage cost tolerance

C.

Work Package cost tolerance

D.

product cost tolerance

Question 129

A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?

Options:

A.

Raise a request for change

B.

Raise an off-specification

C.

Write an Exception Report

D.

Amend the Work Package

Question 130

Which is NOT a purpose of a Benefits Review Plan?

Options:

A.

Define the period over which the cost-benefit analysis will be based

B.

Describe how to measure the performance of the project's products in operational use

C.

Define the scope, timing and ownership of the benefit reviews required

D.

Describe how to measure and confirm any benefits that are to be realised after the project is closed

Question 131

Which is a purpose of an End Project Report?

Options:

A.

Identify individuals or groups that need to be told that the project is coming to an end

B.

Review how well the project performed against the Project Initiation Documentation used to authorize it

C.

Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed

D.

Ensure that key project information is archived and made secure

Question 132

Which is a task of product-based planning?

Options:

A.

Identify activities and dependencies

B.

Write the Project Product Description

C.

Prepare the Work Packages

D.

Produce Product Status Accounts

Question 133

Which of the following statements about stakeholders are true?

1. Someone who thinks they will be affected by a project is a stakeholder on that project.

2. Stakeholders may be internal or external to the corporate organization.

Options:

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 are true

Question 134

Which statement applies to Stage Plans?

Options:

A.

Always have the same duration as the Project Plan

B.

Are produced at the same time as the Project Initiation Documentation

C.

Assist the Project Manager in the day-to-day running and control of the project

D.

Provide a baseline against which the Project Board monitor overall progress

Question 135

What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?

Options:

A.

Directing a Project

B.

Managing a Stage Boundary

C.

Controlling a Stage

D.

Starting up a Project

Question 136

Which is NOT a purpose of the Organization theme?

Options:

A.

Define a project management team structure

B.

Define the level of tolerance for each level of the project management team

C.

Define the Project Board's responsibility for directing the project

D.

Define which role is accountable for the project's success

Question 137

Which statement about stages is true?

Options:

A.

Management stages should be of the same duration

B.

The use of technical stages is mandatory

C.

The use of management stages is mandatory

D.

Management stages are driven by specialist teams

Question 138

From whom does a Team Manager obtain approval for a completed product?

Options:

A.

Project Manager

B.

Project Support

C.

The authority defined in the Product Description

D.

Senior Supplier

Exam Detail
Vendor: PRINCE2
Certification: PRINCE2 Certification
Last Update: Dec 22, 2024
Prince2-Foundation Question Answers