PRINCE2 Prince2-Foundation Actual Questions

PRINCE2 7 Foundation written Exam Questions and Answers

Question 13

Which theme provides all management levels within the project management team with mechanisms for monitoring and control?

Options:

A.

Progress

B.

Change

C.

Organization

D.

Quality

Question 14

Which is an objective of the 'directing a project' process?

Options:

A.

To review and approve a project mandate

B.

To ensure corporate or programme management has an interface to the project

C.

To define how risks, issues and changes will be managed

D.

To obtain approval for completed products

Question 15

To meet the minimum requirements for applying the progress theme, when must the business justification be reviewed?

Options:

A.

At the start of the project

B.

Throughout each stage

C.

When a change is raised

D.

In exception situations

Question 16

Which activity takes place within the Managing a Stage Boundary process?

Options:

A.

Produce Highlight Reports

B.

Take corrective action within the limits of a stage's tolerance

C.

Produce an Exception Plan

D.

Authorize a Stage Plan for the next stage