Question 89

Which process defines the work to deliver the major products ensuring that an organization uses its resources effectively?

Options:

A.

Initiating a project

B.

Starting up a project

C.

Controlling a stage

D.

Managing product delivery

Question 90

Which control is time-driven?

Options:

A.

The creation of a highlight report

B.

The completion of the PID

C.

The creation of an exception report

D.

The end of the financial year

Question 91

What is the BEST reason to perform the risk practice?

Options:

A.

To ensure risks are assigned to people who will own and action them satisfactorily

B.

To establish a supportive risk culture to enable decision-making

C.

To ensure stop-go decisions at stage boundaries are risk-informed

D.

To identiDfy and manage risks to project objectives

Question 92

Which statement describes a purpose of the 'starting up a project’ process?

Options:

A.

To appoint people ta the major rales in the project management team

B.

Ta agree how a team manager will report progress

C.

To provide Information so that the business can understand the cost of delivering the project

D.

To provide management control Listen the project manager and the team managers