Black Friday Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PRINCE2 Certification Prince2-Foundation Full Course Free

PRINCE2 7 Foundation written Exam Questions and Answers

Question 105

Which is a description of a purpose of the 'managing product delivery’ process?

Options:

A.

To agree requirements for the delivery of specific products between the project manager and the team manager

B.

To report progress towards the delivery of a stage’s products to the project board

C.

To recognize that the project has no further contribution make towards achieving project objectives

D.

To plan how the project will approach the work to deliver the project products

Question 106

Which is NOT considered when defining risk tolerance?

Options:

A.

A Project Board's attitude towards risk taking

B.

The allocated risk budget

C.

An organization's risk appetite

D.

The amount of risk a Project Board considers acceptable

Question 107

When should the Project Board refer to corporate or programme management for a decision?

Options:

A.

The stage requires resources

B.

It is forecast that project level tolerance will be exceeded

C.

The Senior Supplier or Senior User needs to be changed

D.

Any request for change needs to be approved

Question 108

Which is a typical core activity within configuration management?

Options:

A.

Quality assurance

B.

Risk management

C.

Verification and audit

D.

Progress reporting