Online Prince2-Foundation Questions Video

PRINCE2 7 Foundation written Exam Questions and Answers

Question 21

Identify the missing words in the following sentence.

The 'directing a project' process starts when [ ? ] and is triggered by the request to initiate a project.

Options:

A.

the 'starting up a project' process is completed

B.

the project mandate has been approved by the project board

C.

the project board has agreed the project strategies

D.

corporate, programme management or the customer have authorized a project

Question 22

What is a benefits management approach used to assess?

Options:

A.

How the project's products have performed when in operational use

B.

The effectiveness of the project strategies

C.

How the project has progressed against its plans

D.

The suitability of the project management team structure

Question 23

Which is a purpose of the Risk Register?

Options:

A.

Describe the risk management techniques and standards to be applied to the project

B.

Act as a central record of information relating to the identified risks for the project

C.

Act as a repository for informal issues

D.

List the responsibilities for achieving an effective risk management procedure

Question 24

Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project's threats and opportunities.

Options:

A.

change budget

B.

project budget

C.

project's cost tolerance

D.

project's risk tolerance