Question 45

Identify the missing words in the following sentence.

Project assurance personnel [ ? ] the project manager.

Options:

A.

are able to overturn the decisions of

B.

must be accountable to

C.

should support

D.

report to the project board and

Question 46

Which is a benefit of using PRINCE2?

Options:

A.

It promotes consistency of project work and the ability to reuse project assets.

B.

It includes techniques for critical path analysis and earned value analysis

C.

It enables a project manager to be accountable for the success of a project

D.

It prevents any changes once the scope of a project has been agreed

Question 47

Which action should the project manager take to ensure effective progress management when a team manager is inexperienced?

Options:

A.

Increase the frequency of checkpoint reports

B.

Allow the team manager more flexibility to exceed cost tolerance

C.

Increase the frequency of event-driven controls

D.

Increase the frequency of escalations by the team manager

Question 48

How does applying the ‘focus on products’ principle help to ensure that stakeholder expectations are met?

Options:

A.

By providing a common understanding of the products required

B.

By providing the tolerances for the project manager’s objectives

C.

By providing roles descriptions for the project management team

D.

By providing the justification for the project