PRINCE2 7 Foundation written Exam Questions and Answers
Question 137
Which statement about stages is true?
Options:
A.
Management stages should be of the same duration
B.
The use of technical stages is mandatory
C.
The use of management stages is mandatory
D.
Management stages are driven by specialist teams
Answer:
C
Explanation:
PRINCE2® mandates the use of management stages in project management. These stages are critical control points used by the Project Board to review progress, assess risks, and make decisions about the project's future. This structure allows for regular monitoring and controlling of the project by breaking it down into manageable sections. References: PRINCE2® Foundation official documentation and study materials.
Question 138
From whom does a Team Manager obtain approval for a completed product?
Options:
A.
Project Manager
B.
Project Support
C.
The authority defined in the Product Description
D.
Senior Supplier
Answer:
A
Explanation:
In the PRINCE2® methodology, the Team Manager obtains approval for a completed product from the Project Manager. The Project Manager is responsible for ensuring that the products delivered by the Team Managers meet the project’s standards and requirements before accepting them. References: PRINCE2® Foundation official documentation and study materials.