in the ‘starting up a project’ process, what is the PRINCE? name for a ‘request for proposal’ received by an external supplier?
Which TWO are objectives of the ‘starting up a project’ process?
1. To create a common view of How the required quality will be achieved
2.To give authority to initiate the project
3. To appoint the resources needed to do the work to initiate the project
4. To ensure that projects are initiated based or agreed acceptance criteria for the project product.
Which process should be Used to confirm that the project continues to deliver against the strategic objectives?
When should the project baseline be updated in order ta meet the purpose of the 'issues' practice?