Black Friday Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

New Release Prince2-Foundation PRINCE2 Certification Questions

PRINCE2 7 Foundation written Exam Questions and Answers

Question 129

A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?

Options:

A.

Raise a request for change

B.

Raise an off-specification

C.

Write an Exception Report

D.

Amend the Work Package

Question 130

Which is NOT a purpose of a Benefits Review Plan?

Options:

A.

Define the period over which the cost-benefit analysis will be based

B.

Describe how to measure the performance of the project's products in operational use

C.

Define the scope, timing and ownership of the benefit reviews required

D.

Describe how to measure and confirm any benefits that are to be realised after the project is closed

Question 131

Which is a purpose of an End Project Report?

Options:

A.

Identify individuals or groups that need to be told that the project is coming to an end

B.

Review how well the project performed against the Project Initiation Documentation used to authorize it

C.

Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed

D.

Ensure that key project information is archived and made secure

Question 132

Which is a task of product-based planning?

Options:

A.

Identify activities and dependencies

B.

Write the Project Product Description

C.

Prepare the Work Packages

D.

Produce Product Status Accounts