Black Friday Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PRINCE2 PRINCE2 Certification Prince2-Foundation New Questions

PRINCE2 7 Foundation written Exam Questions and Answers

Question 33

Which is a purpose of the 'closing a project' process?

Options:

A.

To provide the project board with information to judge the success of a stage

B.

To confirm the project has nothing more to deliver

C.

To establish mechanisms to judge whether the project is still viable

D.

To establish mechanisms for forecasting project objectives

Question 34

Which is a factor when deciding the duration of a management stage?

Options:

A.

The work packages to be delivered

B.

The level of risk in the project

C.

The cost of the stage

D.

The number of products to be produced in the project

Question 35

What information should be recorded in the quality register?

Options:

A.

Planned activities to determine whether the products are fit for purpose

B.

Potential threats to the project's objectives and how they will be managed

C.

Lessons that the project will capture and use during the project

D.

Off-specifications that will occur during the project

Question 36

Which term is defined as the means by which an organization transitions from its current state to the target state?

Options:

A.

Change management

B.

change control

C.

Progress management

D.

Risk management