A project manager is scheduling activities and determines one activity cannot be completed until another
activity is completed. Which of the following dependency relationships is represented?
A critical issue has developed in an active project, and the project manager wants to notify the 20-person global project manager use FIRST to relay this information?
Task A starts on Day 1 and has a duration of two days. Task B has a duration of two days and starts on Day 3.
Task C starts after Task A and has a duration of three days. Task D starts after Task B and Task C and has a
duration of one day. Which of the following represents the critical path?
Which of the following are mutually binding project documents? (Select two.)