11.11 Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Project+ PK0-004 CompTIA Study Notes

Page: 12 / 30
Total 796 questions

CompTIA Project+ Exam Questions and Answers

Question 45

A project manager is scheduling activities and determines one activity cannot be completed until another

activity is completed. Which of the following dependency relationships is represented?

Options:

A.

FF

B.

SS

C.

SF

D.

FS

Question 46

A critical issue has developed in an active project, and the project manager wants to notify the 20-person global project manager use FIRST to relay this information?

Options:

A.

Individually call all project team members.

B.

Send an email to all project team members.

C.

Schedule a conference call.

D.

Schedule a face-to-face meeting.

Question 47

Task A starts on Day 1 and has a duration of two days. Task B has a duration of two days and starts on Day 3.

Task C starts after Task A and has a duration of three days. Task D starts after Task B and Task C and has a

duration of one day. Which of the following represents the critical path?

Options:

A.

Five days

B.

Six days

C.

Seven days

D.

Eight days

Question 48

Which of the following are mutually binding project documents? (Select two.)

Options:

A.

Quotation

B.

Letter of intent

C.

Proposal

D.

Evaluation

E.

Warranty

F.

Charter

Page: 12 / 30
Total 796 questions