Question 93

A milestone task on the critical path has been completed.

Which of the following should the project manager notify?

Options:

A.

Owner of predecessor task

B.

Project team

C.

Project sponsor

D.

Project steering committee

Question 94

A project is about to begin the execution phase. The SOW and project plan have been approved, and the project team has been formed. Which of the following types of meetings should happen NEXT?

Options:

A.

Update

B.

Scheduling

C.

Kickoff

D.

Review

Question 95

A project manager is managing a project with a hard deadline in two weeks. At the current rate of progress, the project will not finish on time.

Which of the following techniques is MOST likely to be used to complete the project on time?

Options:

A.

Throttling

B.

Crashing

C.

Resource leveling

D.

Resource smoothing

Question 96

The project manager of a global project constantly receives complaints from individuals at another location that some team members are not available after lunch on Fridays. This is acceptable to the project manager. Which of the following factors is the MOST likely cause for this scenario?

Options:

A.

Personal preference

B.

Intra-organizational differences

C.

Culture

D.

Time zone

Page: 24 / 30