CompTIA PK0-004 Questions Answers

Page: 6 / 30
Total 796 questions

CompTIA Project+ Exam Questions and Answers

Question 21

For most organizations, which of the following is the MOST efficient method to communicate the project status to a large group of stakeholders?

Options:

A.

Email messages

B.

Internet site

C.

Conference calls

D.

Instant messages

Question 22

In which of the following circumstances would faxing be the MOST appropriate communication method?

Options:

A.

When sending confidential information

B.

When resolving complex issues

C.

When providing weekly status updates

D.

When signatures are required

Question 23

The project manager for a multinational project is evaluating the option of scheduling face quick responses to issues. Which of the following strategies is being applied?

Options:

A.

Risk acceptance

B.

Risk avoidance

C.

Risk transference

D.

Risk mitigation

Question 24

Prior to engaging a vendor on an RFI, which of the following documents protects the company's interests?

Options:

A.

NDA

B.

SLA

C.

MOU

D.

LOI