11.11 Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PK0-004 Questions Bank

Page: 28 / 30
Total 796 questions

CompTIA Project+ Exam Questions and Answers

Question 109

If a project sponsor wants to know the current status and progress of a project, which of the following is the BEST approach to find this information?

Options:

A.

The project sponsor should obtain the current status from team members, put it into a presentation, and present it to the project manager for review.

B.

The scheduler should obtain the current status from team members, apply it to the baseline of the schedule, and run a report.

C.

The scheduler should obtain the current status from team members, update the project charter, project management plan, dashboard, and SOW, and then create a status report to provide to the project manager.

D.

The scheduler should obtain the current status from team members, update the risk register, and provide the information to the project champion for review.

Question 110

A project is in the initiation phase. Which of the following tasks will take place during this phase?

Options:

A.

Develop a WBS.

B.

Define the project requirements.

C.

Create a project charter.

D.

Acquire the project resources.

Question 111

A customer has requested additional features for an active project.

Which of the following steps should take place NEXT?

Options:

A.

Implement the requested changes.

B.

Evaluate the impact of the changes.

C.

Update all project documents.

D.

Submit the requested changes to the CCB.

Question 112

A project team member highlights to the project manager that expensive licensing for critical software in use across the project may expire before the completion project.

Which of the following would the project manager MOST likely do?

Options:

A.

Place a risk on the risk register and arrange a risk review with the appropriate stakeholders to accept and/or mitigate the risk.

B.

Raise a purchase order to purchase the licensing and ask the team member to install it.

C.

Amend the project scope and raise a project change request to obtain approval of the amendment.

D.

Amend the project schedule and work breakdown structures to remove the use of the software from the project.

Page: 28 / 30
Total 796 questions