11.11 Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Free PK0-004 CompTIA Updates

Page: 27 / 30
Total 796 questions

CompTIA Project+ Exam Questions and Answers

Question 105

A project manager does not have enough time to complete several tasks on a critical path. The budget is a low concern. Which of the following should be used to complete the tasks on time?

Options:

A.

Fast-track the tasks.

B.

Utilize positive float.

C.

Crash the schedule.

D.

Remove the critical path

Question 106

A company hires an outside vendor to provide 24/7 support.

Which of the following documents would determine the contractual obligations?

Options:

A.

PO

B.

SLA

C.

LOI

D.

MOU

Question 107

A senior manager asks a project manager for an estimated budget on a new project.

Which of the following is the BEST step for the project manager to take?

Options:

A.

Tell the senior manager the estimation is not available yet.

B.

Use the budget from a similar project to generate estimates.

C.

Ask a SME for an opinion and propose an estimate.

D.

Gather the team to immediately generate estimates.

Question 108

While working on risk ranking, the project team is unsure about the qualitative scales to be used for probability and impact. The project manager directs the team to look in the:

Options:

A.

quality plan.

B.

project management plan.

C.

risk register.

D.

process diagram.

Page: 27 / 30
Total 796 questions