11.11 Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Project+ Changed PK0-004 Questions

Page: 14 / 30
Total 796 questions

CompTIA Project+ Exam Questions and Answers

Question 53

A PM has notified the project team of an immediate project relocation. Of which of the following triggers is this

MOST likely a result? (Choose two.)

Options:

A.

Business continuity response

B.

Resource changes

C.

Disaster recovery response

D.

Risk response

E.

Gate review

Question 54

Which of the following job roles is MOST responsible for providing input on the project requirements, steering

the project, providing expertise, and having vested interest in the project?

Options:

A.

Project scheduler

B.

Project stakeholder

C.

Project team

D.

Project coordinator

Question 55

Gas prices were included in the cost baseline for a transportation and hauling project. Although the estimates

used to create the baseline were based on historical data, which of the following should the project manager

consider as a root cause for potential issues with cost overruns?

Options:

A.

Requirements

B.

Lessons learned

C.

Budget

D.

Environment

Question 56

A project has fallen behind schedule for no obvious reason, so the PM has gathered the team to brainstorm. Which of the following should the PM do NEXT?

Options:

A.

Go over the meetings objectives and agenda.

B.

Brief the team on which tasks have fallen behind schedule and where the project has slack.

C.

Refer to the risk register to map the risks to issues and mitigation strategies.

D.

Review the issue log with the project team and identify potential risks.

E.

Review an Ishikawa diagram with the project team to determine possible causes and effects.

Page: 14 / 30
Total 796 questions