Question 73

A project manager is archiving of project documents.

Which of the following phases does this describe?

Options:

A.

Initiation

B.

Planning

C.

Execution

D.

Closing

Question 74

Which of the following is used to perform a root cause analysis?

Options:

A.

Ishikawa diagram

B.

Bar chart

C.

Pareto diagram

D.

Scatter plot

Question 75

A project team is in the process of risk planning. One of the team members identifies a weather-related risk, which may cause delivery delays.

Which of the following is the BEST risk response strategy?

Options:

A.

Exploit

B.

Enhance

C.

Mitigate

D.

Communicate

Question 76

The project team is not comfortable moving an expensive material.

A third party is hired to move the material. This is an example of risk:

Options:

A.

Transference

B.

Sharing

C.

Avoidance

D.

Acceptance