Question 13

A customer added an additional requirement for a product being developed. Which of the following should the project manager do FIRST?

Options:

A.

Present the change request to the CAB.

B.

Evaluate the change with the project team.

C.

Set up a face-to-face meeting with the project sponsor

D.

Organize a steering committee meeting.

Question 14

During the risk assessment process, the qualitative analysis results in the majority of risk scores being rated as medium.

Which of the following is the BEST course of action?

Options:

A.

Increase the contingency reserve.

B.

Add the risks to the watch list.

C.

Establish and monitor trigger conditions.

D.

Assign the sponsor as the primary risk owner.

Question 15

A cost baseline is used to measure the:

Options:

A.

eventual cost of a project.

B.

increase in the budget.

C.

variance with the initial budget.

D.

inevitable cost overruns.

Question 16

A hurricane occurs in an area where several key project resources are located. When reviewing the project dashboard, the project sponsor sees the project is behind schedule and asks the project manager for an explanation. Which of the following documents should the project manager examine NEXT to provide an explanation?

Options:

A.

Meeting minutes

B.

Issue log

C.

Project schedule

D.

Budget