11.11 Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Free Access CompTIA PK0-004 New Release

Page: 15 / 30
Total 796 questions

CompTIA Project+ Exam Questions and Answers

Question 57

A project manager is assigned a project that is part of the company’s strategic objectives. Of which of the

following is the project a part?

Options:

A.

Project management office

B.

Portfolio

C.

Program

D.

Mission statement

Question 58

An active construction project must make immediate changes when it is discovered that the designated project

area contains protected wetlands.

Which of the following is the MOST likely impact to the project?

Options:

A.

The project quality will decrease

B.

The project scope will decrease

C.

The project timeline will increase

D.

The interproject dependencies will increase

Question 59

Which of the following are mutually binding project documents? (Select two.)

Options:

A.

Quotation

B.

Letter of intent

C.

Proposal

D.

Evaluation

E.

Warranty

F.

Charter

Question 60

A minor change to the baseline schedule is required. This change will be the second minor modification to the schedule. Which of the following is the appropriate version number?

Options:

A.

0.3

B.

1.2

C.

2.0

D.

3.0

Page: 15 / 30
Total 796 questions