Winter Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Free PK0-004 Questions Attempt

Page: 23 / 30
Total 796 questions

CompTIA Project+ Exam Questions and Answers

Question 89

A risk with a high probability and medium consequence to a project has been identified. In response, the project manager has purchased an insurance plan with the intent to provide additional funds if the risk is realized. There is no risk to the schedule or scope. Which of the following types of risk strategies is this an example of?

Options:

A.

Accept risk

B.

Transfer risk

C.

Mitigate risk

D.

Exploit risk

E.

Avoid risk

Question 90

The key stakeholders have reported the project pace as being slow. The project sponsor would like to cancel the project if it cannot be completed before the end of the year. The project is scheduled to be completed three months after the requested date.

To alter the pace of the project, which of the following should the project manager do FIRST?

Options:

A.

Give approval for the change requested by the project sponsor.

B.

Deny the request from the project sponsor.

C.

Document the change request from the project sponsor.

D.

Ask the project sponsor to change the request.

Question 91

A team member learns that an assigned task is not due until the very end of the project. Moreover, the team member is not aware of any predecessor tasks dependent on completing the assigned task. Which of the following does the project manager use to decide if the team member can start the task later or earlier?

Options:

A.

Review the PERT chart and evaluate if the task is a critical dependency.

B.

Review the PERT chart and evaluate if the task is a discretionary dependency.

C.

Review the PERT chart and evaluate if the task is a real dependency.

D.

Review the PERT chart and evaluate if the task is an external dependency.

Question 92

A project has fallen behind schedule. Upon investigation, the project manager determines that team members have implemented requirements relayed via impromptu hallway meetings with the client.

Which of the following should the project manager do to resolve this issue?

Options:

A.

Update the scope management plan.

B.

Modify the project baselines.

C.

Implement change control management.

D.

Inform the stakeholders of the issue.

Page: 23 / 30
Total 796 questions